==List of discussion topics==
+
Back to [[PREX/CREX_Teleconferences]]
  
* Scheduling for PQB time at the end of APEX (CG?!) ''every 6 weeks'' (Starts on 27th Nov)
+
= List of discussion topics =
* Beamline checkout (Ye, Bob) ''every 4 weeks'' (Starts on 27th Nov)
 
  
* Injector setup and feedback (Caryn, Amali) ''every 5 weeks'' (Starts on 4th Dec)
+
{| class="wikitable sortable"
* Beam modulation (Victoria, Ye) ''every 4 weeks'' (Starts on 4th Dec)
+
|+
* GEM detectors (Seamus) "every 4 weeks" (Starts on 4th Dec)
+
! class="unsortable"|<b>Task</b> || class="unsortable"|<b>Responsible</b> || width=40% class="unsortable"|<b>Status </b> ||  class="unsortable"|<b>Update</b> || <b>Next update</b> || class="unsortable"|<b>Link to updates</b>
 
+
|-
* Ion chamber positions (CG) ''every 6 weeks'' (Starts on 11th Dec)
+
|Scheduling for PQB time at the end of APEX || CG || list of tasks is crystalized || every 6 weeks || 01/08/2019 || [[PREX/CREX_Nov_27,_2018_10:00am|Nov 27 2018]]
* Moller polarimeter (Eric, Sanghwa) ''every 4 weeks'' (Starts on 11th Dec)
+
|-
* Data Acquisition (Bob) "every 4 weeks" (Starts on 11th Dec?)
+
|Injector setup and feedback || Caryn, Amali || All set for Jan install of RTP || every 5 weeks || 01/15/2019 || [[PREX/CREX_Dec_11,_2018_10:00am|Dec 11 2018]]
* Tracking and optics (Chandan, Seamus) ''every 4 weeks'' (Starts on 11th Dec)
+
|-
 
+
|Beam modulation || Victoria, Ye || identified cables, will connect and try to send signal to BSY racks || every 4 weeks || 02/05/2019 || [[PREX/CREX_Dec_4,_2018_10:00am|Dec 4 2018]], [[PREX/CREX_Jan_8,_2019_10:00am|Jan 8 2019]]
* Integrating detectors (Dustin) ''every 6 weeks'' (Starts on 18th Dec)
+
|-
* Analyzer (Paul) ''every 4 weeks'' (Starts on 18th Dec)
+
|Design status || Kent || everything on track, deadline for everything to be ready March 11th || every 4 weeks || 01/15/2019 || [[PREX/CREX_Dec_4,_2018_10:00am|Dec 4 2018]]
* Compton polarimeter (Adam, CG) ''every 4 weeks'' (Starts on 18th Dec)
+
|-
 
+
|GEM detectors || Dustin, Seamus || resources at the lab IDed, || every 4 weeks || 01/22/2019 || [[PREX/CREX_Dec_18,_2018_10:00am|Dec 18 2018]]
* Cavity Beam Monitors (Ye) "every 6 weeks" (Starts in January?)
+
|-
* Integrating Beam Monitors (CG?) (Start in January?)
+
|Ion chamber positions || CG || task should be simple. will iterate through simulation || every 6 weeks || 02/05/2019 || [[PREX/CREX_Dec_11,_2018_10:00am|Dec 11 2018]]
 +
|-
 +
|Moller polarimeter || Eric, Sanghwa, Don || comparisons are improving. Bfield inclusion is finished || every 4 weeks || 01/15/2019 || [[PREX/CREX_Dec_11,_2018_10:00am|Dec 11 2018]]
 +
|-
 +
|Data Acquisition || Bob || DAQ upgraded to bank readout. system on track || every 4 weeks || 01/22/2019 || [[PREX/CREX_Dec_11,_2018_10:00am|Dec 11 2018]]
 +
|-
 +
|Tracking and optics || Chandan, Seamus || tracking code needs to be written || every 4 weeks || 01/22/2019 || [[PREX/CREX_Dec_18,_2018_10:00am|Dec 18 2018]]
 +
|-
 +
|Integrating detectors || Dustin, Devi || DAQs setup at JLab, work proceeding on schedule || every 6 weeks || 02/19/2019 || [[PREX/CREX_Jan_8,_2019_10:00am|Jan 8 2019]]
 +
|-
 +
|Analyzer || Paul || several projects being worked on in parallel || every 4 weeks || 01/29/2019 || [[PREX/CREX_Dec_18,_2018_10:00am|Dec 18 2018]], [[PREX/CREX_Jan_29,_2019_10:00am|Jan 29, 2019]]
 +
|-
 +
|Compton polarimeter || Adam, Amali, CG || opened vacuum and replaced mirrors. will try locking || every 4 weeks || 01/15/2019 || [[PREX/CREX_Dec_18,_2018_10:00am|Dec 18 2018]]
 +
|-
 +
|Cavity Beam Monitors || Ye || limited test done using epics readout, working DAC still pending, updated analysis with HRS scalers || every 6 weeks || 02/19/2019 || [[PREX/CREX_Nov_27,_2018_10:00am|Nov 27 2018]], [[PREX/CREX_Jan_8,_2019_10:00am|Jan 8 2019]]
 +
|-
 +
|Integrating Beam Monitors || CG || - || - || 01/08/2019 || -
 +
|}

Latest revision as of 13:43, 4 March 2019

Back to PREX/CREX_Teleconferences

List of discussion topics

Task Responsible Status Update Next update Link to updates
Scheduling for PQB time at the end of APEX CG list of tasks is crystalized every 6 weeks 01/08/2019 Nov 27 2018
Injector setup and feedback Caryn, Amali All set for Jan install of RTP every 5 weeks 01/15/2019 Dec 11 2018
Beam modulation Victoria, Ye identified cables, will connect and try to send signal to BSY racks every 4 weeks 02/05/2019 Dec 4 2018, Jan 8 2019
Design status Kent everything on track, deadline for everything to be ready March 11th every 4 weeks 01/15/2019 Dec 4 2018
GEM detectors Dustin, Seamus resources at the lab IDed, every 4 weeks 01/22/2019 Dec 18 2018
Ion chamber positions CG task should be simple. will iterate through simulation every 6 weeks 02/05/2019 Dec 11 2018
Moller polarimeter Eric, Sanghwa, Don comparisons are improving. Bfield inclusion is finished every 4 weeks 01/15/2019 Dec 11 2018
Data Acquisition Bob DAQ upgraded to bank readout. system on track every 4 weeks 01/22/2019 Dec 11 2018
Tracking and optics Chandan, Seamus tracking code needs to be written every 4 weeks 01/22/2019 Dec 18 2018
Integrating detectors Dustin, Devi DAQs setup at JLab, work proceeding on schedule every 6 weeks 02/19/2019 Jan 8 2019
Analyzer Paul several projects being worked on in parallel every 4 weeks 01/29/2019 Dec 18 2018, Jan 29, 2019
Compton polarimeter Adam, Amali, CG opened vacuum and replaced mirrors. will try locking every 4 weeks 01/15/2019 Dec 18 2018
Cavity Beam Monitors Ye limited test done using epics readout, working DAC still pending, updated analysis with HRS scalers every 6 weeks 02/19/2019 Nov 27 2018, Jan 8 2019
Integrating Beam Monitors CG - - 01/08/2019 -