This was for the <font color="magenta">PREX-I run in 2010</font>.  Run plans for PREX-II and C-REX will be forthcoming.
+
[[PREX I Run Plans]]
 
 
This was the daily run plans prior to June 7, 2010.  Run plans after June 7 are found here: &nbsp; [[RunPlanDaily]]
 
 
 
{| border="1"
 
|+ Daily Run Plan for PREX &nbsp; <font color="blue">(latest at bottom)</font>
 
! Date (2010) !! Shift !!---------- Activity (Responsible) ----------!!---&nbsp;Status&nbsp;---
 
|-
 
| 03/19
 
| Day
 
| pump down; Møller, Compton, septum install; Q2 repair<br />
 
Insert sieve. (Techs)
 
|done
 
|-
 
| 03/19
 
| Swing
 
| Beam restore (B-team)
 
| done
 
|-
 
| 03/20
 
| Owl
 
|
 
* Septum checkout (Michaels: Page when beam imminent & spectrometer ready)
 
also:
 
* Initial look at low current cavity monitors (Ahmed: Page when beam imminent & spectrometer ready)
 
* Target alignment (Michaels)
 
* VDC checkout (Michaels)
 
* Quartz detectors checkout (McNulty, Wexler -- page when VDC tracks seen)
 
* GEM checkout (Camsonne -- page when VDC tracks seen, if left dipole is operating)
 
| done
 
----
 
All at 1-2 µA.<br />
 
Scattered energy ~ beam energy = 1.063 GeV.<br />
 
Quad settings:
 
*Right arm:
 
** Q1: dI/dP= 411.2474 Amps/GeV/c
 
** Q2: dI/dP= 436.2014 Amps/GeV/c
 
** Q3: dI/dP= 433.3897 Amps/GeV/c
 
* Left Arm:
 
** Q1: dI/dP= 419.8772 Amps/GeV/c
 
** Q2: dI/dP= 435.6273 Amps/GeV/c
 
** Q3: dI/dP= 434.9682 Amps/GeV/c
 
"Usual" polarity
 
|-
 
| 03/20
 
| Day
 
| Beam off & hall open 9:00 am<br />
 
Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs)
 
| done
 
|-
 
| 03/20
 
| Swing
 
|
 
* Close up hall
 
* Benesch tuning (1/2 - 2 hours)
 
* Verify quad polarities (Camsonne)
 
* Cavity monitors basic function test (Ahmed)
 
* Low current cavity monitors setup (Musson, Ahmed)
 
| done
 
|-
 
| 3/21
 
| Owl
 
|
 
* Low current cavity monitors setup (Musson, Ahmed)
 
* Access for GEM installation (Camsonne)
 
| done but GEMs not ready
 
|-
 
| 3/21
 
| Day
 
|
 
* Spectrometer checkout:
 
** Quartz detectors checkout (McNulty, Wexler)
 
** Lumi checkout (Mercado) (2 µA on Ta)
 
** GEM checkout (Camsonne?)
 
* A line tuning (Benesch)
 
* Raster checkout
 
* Access:
 
** Low current cavities
 
** Target position
 
** Quartz
 
** Scintillator alignment
 
** LQ2
 
| done
 
|-
 
| 3/21
 
| Swing
 
|
 
* Low current cavity monitors setup (Michaels, Ahmed)
 
* Remove sieves
 
* Initial look at sieve out data
 
* Replace sieves
 
| done
 
|-
 
| 3/22
 
| Owl
 
|
 
* Pointing measurement (Riordan)
 
* Remove sieves
 
* Repeat pointing measurements with no sieves
 
* If done or unable to continue before 4 am page Luis Mercado to do lumi checks
 
* After 4 am page Dustin McNulty for detector work
 
|done
 
|-
 
| 3/22
 
| Day
 
|
 
* Optics (Liyanage) Sieve OUT.  NB Current limit 2 uA!
 
|done
 
|-
 
| 3/22
 
| Swing
 
|
 
* Optics continued, sieve IN.  NB Current limit 2 uA! (Shift Crew)
 
|done
 
|-
 
| 3/23
 
| Owl
 
|
 
* Quartz detectors resolution studies (KK, Dustin, John W)
 
* Lumi studies (Luis)
 
|done
 
|-
 
| 3/23
 
| Day
 
|
 
* Remove water target. (Target, Techs)
 
* Reconfigure Moller cryo.
 
* '''Beam studies''' ~ 2pm, study of helicity correlated position differences for spin flipper states. (Dalton, Rupesh, Reza)
 
|water cell removed, rest not finished
 
|-
 
| 3/23
 
| Swing
 
|
 
* Target pumpdown
 
|done
 
|-
 
| 3/24
 
| Owl
 
|
 
* Target pumpdown
 
|done
 
|-
 
| 3/24
 
| Day
 
|
 
* Target cooldown
 
|done
 
|-
 
| 3/24
 
| Swing
 
|
 
* Tune high current beam into Hall A
 
|done
 
|-
 
| 3/25
 
| Owl
 
|
 
* Commission lead target, 50 uA (Bob)
 
* Lumis and oversampling tests (KK, Luis, Paul)
 
|in progress
 
|-
 
| 3/25
 
| Day
 
|
 
* Access to fix left dipole
 
|done
 
|-
 
| 3/25
 
| Swing
 
|
 
* Parity Quality commissioning (Kent, Rupesh, Luis, Dustin)
 
* Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng)
 
|postponed
 
|-
 
| 3/26
 
| Owl
 
|
 
* High Luminosity Detector Commissioning
 
|in progress
 
|-
 
| 3/26
 
| Day
 
|
 
*Moller Checkout
 
|postponed
 
|-
 
| 3/26
 
| Swing
 
|
 
*High Current on C12 (thick and thin)
 
|partly done
 
|-
 
| 3/27
 
| Owl
 
|
 
| no beam
 
|-
 
| 3/27
 
| Day
 
|
 
| no beam
 
|-
 
| 3/27
 
| Swing
 
|
 
*High-current on thick C12, adjust HV (Luis or Bob)
 
*Finish the commissioning of thick Pb target (Bob, Ahmed)
 
*Electronic Commissioning (KK, Luis, Paul, Jon et al)
 
|done, high-current tests continue
 
|-
 
| 3/28
 
| Owl
 
|
 
*Continue with the above, if necessary.
 
*High Luminosity Commissioning (Rupesh, Luis, Jon, Bob)
 
*BCM/BPM calibration (Rupesh)
 
*Establishing Parity Measurements, Charge feedback, blinding (Rupesh, Jon)
 
|not finished
 
|-
 
| 3/28
 
| Day
 
|
 
*Comparison Study of Optics Tunes (Seamus, Nilanga, Kiad)
 
*Sometime before Monday, submit the ATLIS plan for Dithering test (Rupesh)
 
|done
 
|-
 
| 3/28
 
| Swing
 
|
 
*Continue Optics if necessary.
 
*Continue High Luminosity Commissioning
 
|done
 
|-
 
| 3/29
 
| Owl
 
|
 
*Mini-production run (shift crew)
 
*Stop beam at 07:00 or whenever Ed Folts asks to.
 
|done
 
|-
 
| 3/29
 
| Day
 
|
 
*Open Hall A to set up Moller and Compton (Ed Folts, Sasha, Sirish, et.al.)
 
*Work on GEMs (Alex, Seamus, et.al.)
 
*MCC to do beam studies while Hall A open
 
*Detector linearity/LED tests (Luis)
 
*Setup WAC analysis (Mark, Mindy)
 
|done
 
|-
 
| 3/29
 
| Swing
 
|
 
*Moller magnet cooldown
 
*Optics and acceptance studies (Seamus, Ahmed, Nilanga)
 
|done
 
|-
 
| 3/30
 
| Owl
 
|
 
*Commission charge feedback (Mark)
 
*Current monitor calibration and pedestals determination (Mark)
 
*Quasi-production on Empty Target (owl shift crew)
 
|done
 
|-
 
| 3/30
 
| Day
 
|
 
*Access do work on Moller and Compton.
 
*Some GEM installation work. (Alex, Seamus, Kiad, Nilanga)
 
*Possible linearity/LED study. (Luis)
 
|done, except linearity
 
|-
 
| 3/30
 
| Swing
 
|
 
*First Commissioning of Moller -- Beam Checks (Sasha, Javier, Roman, Jay)
 
|done
 
|-
 
| 3/31
 
| Owl
 
|
 
*Scans of Septum and quad Q1 for tunes A and B. (Bob)
 
*Beam Studies of Helicity Correlations
 
|done
 
|-
 
| 3/31
 
| Day
 
|
 
*Beam Tuning (Jay Benesch)
 
|done
 
|-
 
| 3/31
 
| Swing
 
|
 
*Either or both of these:
 
* a) Moller Commissioning (Sasha, Javier, Roman, Jay)
 
* b) Tests of Dithering and other Beam-Related things (Kent, Rupesh)
 
|Moller was done
 
|-
 
| 4/1
 
| Owl
 
|
 
*If Kent's tests not done on Swing, continue here. (Kent, Rupesh)
 
*Beam and Septum scan with new tune (Seamus)
 
*Helicity-correlated beam studies (Shift crew)
 
|done
 
|-
 
| 4/1
 
| Day
 
|
 
* Beam Tuning (Jay)
 
|done, successful
 
|-
 
| 4/1
 
| Swing
 
|
 
* More beam tuning if necessary
 
* Moller Commissioning
 
|done
 
|-
 
| Friday 2 April
 
| Owl
 
|
 
*Assuming the HRS tune has been frozen
 
*Check detector alignment
 
*A_T studies
 
*Q<sup>2</sup> Measurements
 
|partly done, needs more work
 
|-
 
| Friday 2 April
 
| Day
 
|
 
*Tuning Beam for Compton
 
|done
 
|-
 
| Friday 2 April
 
| Swing
 
|
 
*  20:00 Obtain sieve runs (optics mini-run plan), Q<sup>2</sup> measurements (Bob)
 
|done, but not Q<sup>2</sup>
 
|-
 
| Saturday 3 April
 
| Owl
 
|
 
* Obtain sieve runs on Ta (Nilanga mini-run plan)
 
* Put in Lead target at low current and do counting-mode runs (Rupesh, Ahmed)
 
* Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
 
|done
 
|-
 
| Saturday 3 April
 
| Day
 
|
 
* Moller Commissioning <font color="green">(priority activity)</font>
 
* Work on getting into production mode (Mark, Rupesh)
 
|done, but not yet in prod.
 
|-
 
| Saturday 3 April
 
| Swing
 
|
 
* Moller commissioning
 
|done
 
|-
 
| Sunday 4 April
 
| Owl
 
|
 
* Counting data on tune Y (right arm) super-thin carbon
 
* Change to tune B
 
* Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
 
|done
 
|-
 
| Sunday 4 April
 
| Day
 
|
 
* Integrate-mode with thick carbon 50 uA
 
* Compton QWP1 calibration.
 
|done
 
|-
 
| Sunday 4 April
 
| Swing
 
|
 
* General Compton commissioning and pseudo-production (empty target) parity data at 50 uA.
 
|done
 
|-
 
| Monday 5 April
 
| Owl
 
|
 
* pseudo-production (empty target) parity data and Compton data at 50 uA.
 
|done
 
|-
 
| Monday 5 April
 
| Day
 
|
 
* 12:00 Jay to run optics test (~ 30 mins)
 
* Moller Spin Dance
 
* Set up vertical polarization and measure A_T
 
|done
 
|-
 
| Monday 5 April
 
| Swing
 
|
 
*Continue to setup up vertical polarization
 
*Measurements of A_T on Pb and C12
 
|done
 
|-
 
| Tuesday 6 April
 
| Owl
 
|
 
* Continue measurements of A_T on Pb and C12
 
|partly done
 
|-
 
| Tuesday 6 April
 
| Day
 
|
 
* Possible horizontal scan:  Tune B with sieve slit (Seamus)
 
* When ready: Relocate Quartz Detectors (Dustin, Jack)
 
|postponed: vacuum problems
 
|-
 
| Tuesday 6 April
 
| Swing
 
|
 
* In restricted access.
 
* Any activities that require access.
 
* Shift canceled
 
|
 
|-
 
| Wednesday 7 April
 
| Owl
 
|
 
* Shift cancelled
 
|
 
|-
 
| Wednesday 7 April
 
| Day
 
|
 
*Shift cancelled
 
* Investigate target vacuum problem
 
* Move quartz detectors (Dustin, Jack)
 
|Leak found at O-ring connection between target chamber and collimator box
 
|-
 
| Wednesday 7 April
 
| Swing
 
|
 
*Shift cancelled
 
|
 
|-
 
| Thursday 8 April
 
| Owl
 
|
 
*Shift cancelled
 
|
 
|-
 
| Thursday 8 April
 
| Day
 
|
 
*Shift cancelled
 
|Target chamber open, found that the 4th foil in Optics target blown off
 
|-
 
| Thursday 8 April
 
| Swing
 
|
 
*Shift cancelled
 
|
 
|-
 
| Friday 9 April
 
| Owl
 
|
 
*Shift cancelled
 
|
 
|-
 
| Friday 9 April
 
| Day
 
|
 
* To be determined.
 
* When ready: Install GEMs
 
|
 
|-
 
| Friday 9 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Saturday 10 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Saturday 10 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Saturday 10 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Sunday 11 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Sunday 11 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Sunday 11 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Monday 12 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Monday 12 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Monday 12 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Tuesday 13 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Tuesday 13 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Tuesday 13 April
 
| Swing
 
|
 
* Cancelled
 
|Tungsten collimator modified and installed.  Target pump down started and initially successful.
 
|-
 
| Wednesday 14 April
 
| Owl
 
|
 
* Cancelled
 
| Target pump down.
 
|-
 
| Wednesday 14 April
 
| Day
 
|
 
* Cancelled -- no shift workers (might need a TO)
 
* Target pump down and leak checking.
 
* When ready, begin target cooldown. (Dave Meekins and JP)
 
| Done.  Vacuum good.  Target cold.
 
|-
 
| Wednesday 14 April
 
| Swing
 
|
 
* Beam restore in Hall A
 
* Harp Scan - Shifters
 
* Raster size scan (goal is 3x3mm on empty cell) - Shifters.
 
* Detector Alignment - Dustin
 
* Dithering run with Septum On/Off - Rupesh.
 
|
 
|-
 
| Thursday 15 April
 
| Owl
 
|
 
<!--#* Beam restore in Hall A
 
#* When ready, begin <font color="blue">PREX recovery program:</font>
 
#* Check alignment of collimator.  Check temperature vs beam current. (Bob)
 
#* Check alignment of PREX quartz detector. (Dustin)
 
#* Check alignment of sieve slits, verify they did not change. (Seamus or Bob)
 
* Check alignment of Pb/diamond target and optimal raster size. (Bob)-->
 
* Thick Carbon Integrating Mode Run - Rupesh.
 
* Thick Carbon Dithering Run - Rupesh + Luis.
 
* Take Access: Change to counting mode and put sieve in - Ahmed.
 
|
 
|-
 
| Thursday 15 April
 
| Day
 
|
 
* Beam Studies -- establishing good beam in Hall A and Compton (Jay and B team)
 
|
 
|-
 
| Thursday 15 April
 
| Swing
 
|
 
* Detector Alignment - Dustin.
 
* Pb Alignment - Bob.
 
* Take access and put sieve in - Seamus.
 
* Sieve Alignment - Seamus.
 
* Take Access to remove sieve (Seamus) + switch to integrating mode (Jon) - '''Page Guy and Bob'''.
 
* Heat load test '''(run up to 500C)''' - Bob + Guy.
 
If possible, depending on heat load test:
 
* Relative Rate 12C/Pb Runs - Bob / Dustin.
 
* Start production (Rupesh, Luis, Kent, Krishna)
 
|
 
|-
 
| Friday 16 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Friday 16 April
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Friday 16 April
 
| Swing
 
|
 
* Production @ 40uA
 
* Ramp up to 50uA (Guy + Bob)
 
|
 
|-
 
| Saturday 17 April
 
| Owl
 
|
 
* Production @ 50uA
 
|
 
|-
 
| Saturday 17 April
 
| Day
 
|
 
* Production @ 50uA
 
* Moller Checks + Measurement Starting 9am (Sasha)
 
|
 
|-
 
| Saturday 17 April
 
| Swing
 
|
 
* Moller till 7pm (Sasha).
 
* Compton (Jay Benesch + Megan).
 
* Production @ 50uA.
 
|
 
|-
 
| Sunday 18 April
 
| Owl
 
|
 
* Production @ 50uA
 
|
 
|-
 
| Sunday 18 April
 
| Day + Swing
 
|
 
* Production @ 50uA.
 
* Staring 3pm:
 
# Compton test (Jay Benesch + Megan).
 
# Page Dustin + Jon + Bob + Sasha.
 
# Q^2 Measurement (Bob)
 
# Call Compton Experts
 
# Access:
 
## Refill Moller Magnet.
 
## Check Compton HV.
 
## Remove S0.
 
## Go to counting mode (Dustin).
 
## Compton Stuff.
 
## Detector Mapping (Jon).
 
# Detector Alignment (Dustin).
 
# Q^2 Measurement (Bob).
 
# Relative Rate Measurement (Bob).
 
# Access to Return to Integrating Mode.
 
* Production @ 50uA
 
|-
 
| Monday 19 April
 
| Owl
 
|
 
* Production @ 50uA
 
|
 
|-
 
| Monday 19 April
 
| Day
 
|
 
* Production @ 50uA
 
|
 
|-
 
| Monday 19 April
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Tuesday 20 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Tuesday 20 April
 
| Day
 
|
 
* Production
 
* Beam studies from approx. 11 am to 2 pm
 
* Hall A Activities:
 
* -- Compton 1/4wave stepper (Abdurahim)
 
* -- Check R-HRS Q2 and switch to remote mode (Heidi)
 
* -- Adjust R-HRS A_T (Dustin)
 
* -- Take pedestal data (Jon)
 
* -- Check 4th GEM and possibly install 5th (Alex, Jon)
 
* -- Test motion of A_T detector R-HRS (Jon)
 
* -- Possible Compton shielding / HV check (Megan)
 
* -- Ramp Moller magnet, measure stray fields. (Sasha)
 
* -- Parasitic work on floor (Yi Qiang)
 
|
 
|-
 
| Tuesday 20 April
 
| Swing
 
|
 
* Tune up Compton
 
* Production
 
|
 
|-
 
 
 
| Wednesday 21 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Wednesday 21 April
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Wednesday 21 April
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Thursday 22 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Thursday 22 April
 
| Day
 
|
 
* Beam studies.  Transverse Phase Space Study in Wien.  (Reza, Mark, Rupesh)
 
* At ~2 pm start Moller commissioning
 
|
 
|-
 
| Thursday 22 April
 
| Swing
 
|
 
* Finish Moller (10 hours)
 
* Resume Production
 
* Don't forget the beam recovery procedure
 
|
 
|-
 
| Friday 23 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Friday 23 April
 
| Day
 
|
 
* Q<sup>2</sup> Studies (3 hrs) -- Dustin, Bob
 
* GEM studies are only parasitic.
 
|
 
|-
 
| Friday 23 April
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Saturday 24 April
 
| Owl
 
|
 
* Production on thick C12
 
|
 
|-
 
| Saturday 24 April
 
| Day
 
|
 
* Production on thick C12
 
* At about 2 pm switch to 120 Hz, still C12
 
* Run briefly on C12 at 120 Hz
 
* Switch to thick Pb target (120 Hz)
 
|
 
|-
 
| Saturday 24 April
 
| Swing
 
|
 
* Production on Pb at 120 Hz
 
|
 
|-
 
| Sunday 25 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Sunday 25 April
 
| Day
 
|
 
* Q<sup>2</sup> measurements - Bob, Dustin
 
* Otherwise production
 
|done
 
|-
 
| Sunday 25 April
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Monday 26 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Monday 26 April
 
| Day
 
|
 
* Wien flip
 
|Wien flip postponed until Tues
 
|-
 
| Monday 26 April
 
| Swing
 
|
 
* Production
 
|-
 
| Tuesday 27 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Tuesday 27 April
 
| Day
 
|
 
* Beam Studies
 
* Wien Flip
 
* Checks of laser at polarized source (Kent and EGG)
 
* Adiabatic Damping Study (Yves Roblin)
 
|
 
Done
 
|-
 
| Tuesday 27 April
 
| Swing
 
|
 
* Compton Tune
 
* 4 hrs on Thick Carbon (RD=0, IT=500us)
 
* flip half-wave plate
 
* 4 hrs on Thick Carbon
 
|
 
|-
 
| Wednesday 28 April
 
| Owl
 
|
 
* Finish Swing Plan
 
* Yves Roblin Measurement (if possible)
 
* Run on Carbon (RD=0, IT=1535)
 
|
 
|-
 
| Wednesday 28 April
 
| Day
 
|
 
* Moller
 
|
 
|-
 
| Wednesday 28 April
 
| Swing
 
|
 
* Finish Moller
 
* Production
 
|
 
|-
 
| Thursday 29 April
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Thursday 29 April
 
| Day
 
|
 
* Production
 
|Access to repair target leak
 
|-
 
| Thursday 29 April
 
| Swing
 
|
 
* Production
 
|Could not close hall due to faulty fire suppression system
 
|-
 
| Friday 30 April
 
| Owl
 
|
 
* Production
 
|Could not close hall due to faulty fire suppression system
 
|-
 
| Friday 30 April
 
| Day
 
|
 
* 08:00 Beam Stops for Open House
 
|
 
|-
 
| Friday 30 April
 
| Swing
 
|
 
* No Beam
 
* Injector studies
 
|
 
|-
 
| Friday 30 April
 
| Owl
 
|
 
* No Beam
 
* Injector studies
 
|
 
|-
 
| Saturday 1 May
 
| Day
 
|
 
* Open House
 
* Detector work
 
* Compton work
 
|
 
|-
 
| Saturday 1 May
 
| Swing
 
|
 
* Restore Beam. 
 
* Check Beam Properties.  (shift)
 
* Pulsed Beam Test. (Mark, Luis)
 
|
 
|-
 
| Sunday 2 May
 
| Owl
 
|
 
* Continue with Above Tests
 
* Raster and Pb Target Tests (Bob)
 
|
 
|-
 
| Sunday 2 May
 
| Day
 
|
 
* Continue Above Tests if necessary
 
* Start Production
 
* Get cavities to work at high current.  (Ahmed)
 
* (The check of cavities at low current is postponed.)
 
|
 
|-
 
| Sunday 2 May
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Monday 3 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Monday 3 May
 
| Day
 
|
 
* Hall B Pass change 3 -> 5 until ~1:00PM
 
* Compton vacuum, LHRS dipole UPS replacement during the down
 
* Bake compton chicane overnight during production, run beam straight through
 
* Return to PbD #2 production
 
* Large asymmetry run (Jon)
 
|
 
*
 
* Baking started, HRS work completed by Heidi
 
|-
 
| Monday 3 May
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Tuesday 4 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Tuesday 4 May
 
| Day
 
|
 
* Work on switch for Pockels cell (start 9:00AM)
 
* Complete Compton beam line bake-out, leak check, cavity alignment
 
|
 
* Pockels cell switch work complete
 
* Compton vacuum reopened
 
|-
 
| Tuesday 4 May
 
| Swing
 
|
 
* Production
 
|
 
* Continued Compton realignment/laser polarization measurement
 
|-
 
| Wednesday 5 May
 
| Owl
 
|
 
* Production
 
|
 
* Stopped work on Compton - still not complete
 
* Changed beam spot size to 200x200um
 
|-
 
| Wednesday 5 May
 
| Day
 
|
 
* 12 hours Moller tests, start 9:00AM  (Sasha, Jixie)
 
|
 
|-
 
| Wednesday 5 May
 
| Swing
 
|
 
* Finish Moller tests, 21:00
 
* Raster clock tests 22:00-24:00 (KK, Bob, Jon)
 
* Production as per raster clock tests
 
|
 
|-
 
| Thursday 6 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Thursday 6 May
 
| Day
 
|
 
* Beam Studies (8 hours controlled access starting 08:15)
 
** Finish Compton cavity work (Sirish, Abdurahim)
 
** Start Compton pumping, replace leaky upstream valve? (John Heckman et al)
 
** Remove GEM(s)?? (Alex, Kiad)
 
** Compton Boron installation (Megan)
 
|
 
* Continued compton cavity alignment
 
* Boron installed
 
* INFN GEMs removed to EEL, (additional UVA GEM installed?
 
|-
 
| Thursday 6 May
 
| Swing
 
|
 
* Raster clock tests
 
* Production
 
|
 
* CHL trip
 
|-
 
| Friday 7 May
 
| Owl
 
|
 
* Raster clock tests (cont?)
 
* Production
 
|
 
* Tests aborted due to network switch failure in the hall
 
|-
 
| Friday 7 May
 
| Day
 
|
 
* Production
 
* Wien flip, QE scan, spot move (nominally 9:00AM)
 
|
 
* Wien flip, QE scan, spot move completed. 
 
* Compton valve work continued until 2:00
 
* Started detector alignment checks
 
* Q<sup>2</sup> and establish low-current cavities (Dustin)
 
|-
 
| Friday 7 May
 
| Swing
 
|
 
* Tests by KK et al
 
* Production
 
|
 
|-
 
| Saturday 8 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Saturday 8 May
 
| Day
 
|
 
* Production
 
* 2:00PM - Turn off cavity baking
 
* 3:00PM - Leak check, turn on ion pumps
 
* 4:00PM - Routine Moller Measurement
 
|
 
* Compton vacuum reestablished
 
* Replaced valve opens with sufficient vacuum levels
 
|-
 
| Saturday 8 May
 
| Swing
 
|
 
* Moller
 
|
 
* Moller measurement gives 91% polarization
 
|-
 
| Sunday 9 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Sunday 9 May
 
| Day
 
|
 
* Compton ready?
 
* Production
 
|
 
* Cavity locks at 3kW!
 
* Valve upstream of chicane will not open
 
|-
 
| Sunday 9 May
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Monday 10 May
 
| Owl
 
|
 
* Production
 
|
 
* Left dipole down
 
* Compton valve stuck
 
|-
 
| Monday 10 May
 
| Day
 
|
 
* Fix left dipole
 
* Fix Compton valve
 
* Fix target vacuum
 
|
 
* Left dipole down
 
* Compton valve fixed and tested
 
* Target vacuum bad
 
|-
 
| Monday 10 May
 
| Swing
 
|
 
* Standby
 
* Empty or C target oversampling runs if valves can be opened
 
* 1-arm production if target vacuum < 5E-5
 
|
 
* Left dipole down
 
* Target vacuum bad
 
|-
 
| Tuesday 11 May
 
| Owl
 
|
 
* Standby
 
* Empty or C target oversampling runs if valves can be opened
 
* 1-arm production if target vacuum < 5E-5
 
|
 
|-
 
| Tuesday 11 May
 
| Day
 
|
 
* Wien flip
 
* Beam studies -- injector studies
 
* Raster setup
 
* Fix left dipole
 
* Fix target vacuum
 
|
 
|-
 
| Tuesday 11 May
 
| Swing
 
|
 
* Compton tune
 
* Oversampling tests
 
|
 
* Left dipole down
 
* Right dipole NMR down
 
* Target vacuum bad
 
|-
 
| Wednesday 12 May
 
| Owl
 
|
 
* Production
 
|
 
* Left dipole down
 
* Right dipole NMR down
 
* Target vacuum bad
 
|-
 
| Wednesday 12 May
 
| Day
 
|
 
* Repair left dipole PS
 
* Repair right dipole NMR
 
* Repair right Q3 bad bit
 
|
 
* Target vacuum bad
 
|-
 
| Wednesday 12 May
 
| Swing
 
|
 
* Standby
 
|
 
* Left dipole down
 
* Left Q3 controls problem
 
* Target vacuum bad
 
|-
 
| Thursday 13 May
 
| Owl
 
|
 
* Standby
 
|
 
* Left dipole down
 
* Left Q3 controls problem
 
* Target vacuum bad
 
|-
 
| Thursday 13 May
 
| Day
 
|
 
* Repair left dipole PS
 
* Repair left Q3 controls
 
* Find and stop target vacuum leak
 
* Warm up target
 
|
 
|-
 
| Thursday 13 May
 
| Swing
 
|
 
* Warm up target
 
|
 
|-
 
| Friday 14 May
 
| Owl
 
|
 
* Pump down target
 
|
 
|-
 
| Friday 14 May
 
| Day
 
|
 
* Pump down target
 
|
 
|-
 
| Friday 14 May
 
| Swing
 
|
 
* Cool target
 
* Re-establish beam
 
* Raster tests
 
|
 
* Target vacuum good
 
* Both spectrometers good
 
|-
 
| Saturday 15 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Saturday 15 May
 
| Day
 
|
 
* Access for left dipole regulation
 
|
 
* Left dipole regulation failed
 
* Target vacuum increase, then decrease with added heating
 
|-
 
| Saturday 15 May
 
| Swing
 
|
 
* Access for left dipole regulation
 
* Re-establish beam
 
* Møller
 
|
 
* Left dipole regulation bad
 
* Target vacuum varying, mostly < 1e5
 
|-
 
| Sunday 16 May
 
| Owl
 
|
 
* Møller
 
|
 
* Left dipole regulation bad
 
* Target vacuum varying, mostly < 1e5
 
|-
 
| Sunday 16 May
 
| Day
 
|
 
* Access for left dipole regulation
 
|
 
* Target vacuum varying, mostly < 1e5
 
|-
 
| Sunday 16 May
 
| Swing
 
|
 
* Production
 
* Background test (L PMTs on)
 
|
 
* Left dipole regulation bad
 
* Target vacuum varying, mostly < 1e5
 
|-
 
| Monday 17 May
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Monday 17 May
 
| Day
 
|
 
* Controlled Access for Left Dipole fix
 
* Moller refilled
 
|
 
* Left dipole working for now
 
* Suspect bad silicon-controlled rectifier (SCR)
 
* There are 12 needed and only 6 spares
 
* Looking for spares and will work during beam studies Tue.
 
|-
 
| Monday 17 May
 
| Swing
 
|
 
* Production with both arms!
 
|
 
|-
 
| Tuesday 18 May
 
| Owl
 
|
 
* Production (hopefully with both arms!)
 
|
 
* No Left Dipole issues all night
 
|-
 
| Tuesday 18 May
 
| Day
 
|
 
* Beam Studies, beginning 9am (8hrs)
 
* Wien Flip
 
* Maintenance on the Left Dipole Power supply
 
|
 
* Wien Flip completed before beam studies
 
* Beam studies completed
 
* Measurements performed on Left Dipole Power supply
 
|-
 
| Tuesday 18 May
 
| Swing
 
|
 
* Production
 
* Oversample tests (Rupesh)
 
|
 
* Compton not done
 
* Oversample tests not done
 
|-
 
| Wednesday 19 May
 
| Owl
 
|
 
* Production
 
* Oversample tests
 
|
 
* Oversample tests completed
 
|-
 
| Wednesday 19 May
 
| Day
 
|
 
* Compton Tuning (1-2hrs, start around 10am)
 
* Raster tests during 'target vacuum recovery'
 
* Production
 
|
 
* Injector tuning did not help Compton rates
 
* Jay and Yan are asking for advice
 
* Compton tuning during beam studies tomorrow
 
|-
 
| Wednesday 19 May
 
| Swing
 
|
 
* Production
 
* Q2 and detector alignment (2-3hrs, around 8pm)
 
|
 
* short Q2 measurement
 
* Target vacuum tripped valves closed -> no beam
 
|-
 
| Thursday 20 May
 
| Owl
 
|
 
* Production
 
|
 
* No beam - target operator only
 
|-
 
| Thursday 20 May
 
| Day
 
|
 
* Beam Studies (start at 8:30am, afternoon for Compton tuning)
 
* Some measurements on left dipole power supply by Jack in Hall
 
* Production
 
|
 
* Compton tuning needs to be rescheduled
 
* Jack did some work in hall
 
|-
 
| Thursday 20 May
 
| Swing
 
|
 
* Canceled
 
| We lost the target vacuum.  Will need to warm up target and replace O-ring after letting radiation subside.  Plan to replace O-ring on Monday May 24.
 
|-
 
| Friday 21 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Friday 21 May
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Friday 21 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Saturday 22 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Saturday 22 May
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Saturday 22 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Sunday 23 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Sunday 23 May
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Sunday 23 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Monday 24 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Monday 24 May
 
| Day
 
|
 
* Various tests
 
**Pedestal runs
 
**linearity studies
 
**detector time constant tests
 
**GEM studies
 
* Target repairs - replace o-ring with silicon one temporarily
 
* Keep target warm and pump down
 
* Leak check
 
|
 
|-
 
| Monday 24 May
 
| Swing
 
|
 
* Pedestal runs
 
|
 
|-
 
| Tuesday 25 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Tuesday 25 May
 
| Day
 
|
 
* Beam Studies (until between 10am and noon)
 
* Pedestal runs
 
|Kalres O-ring installed ahead of schedule.  Pumping down.
 
|-
 
| Tuesday 25 May
 
| Swing
 
|
 
* Pedestal runs
 
|
 
|-
 
| Wednesday 26 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Wednesday 26 May
 
| Day
 
|
 
* Accelerator Vacuum Group in Hall for Leak checks
 
* Switch box arrived for activate remotely the heating and cooling of thetarget
 
|
 
* Found a leak, but pressure stable at 675 mtor
 
* Electrician will install the appropriate outlet; R. Michaels is working on the remote control.
 
|-
 
| Wednesday 26 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Thursday 27 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Thursday 27 May
 
| Day
 
|
 
* Accelerator Vacuum Group in Hall for Leak checks
 
|
 
|-
 
| Thursday 27 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Friday 28 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Friday 28 May
 
| Day
 
|
 
* Shift workers on Standby
 
* Accelerator Vacuum Group in Hall for Leak checks
 
|
 
|-
 
| Friday 28 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Saturday 29 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Saturday 29 May
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Saturday 29 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Sunday 30 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Sunday 30 May
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Sunday 30 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Monday 31 May
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Monday 31 May
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Monday 31 May
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Tuesday 1 June
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Tuesday 1 June
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Tuesday 1 June
 
| Swing
 
|
 
* Canceled
 
|
 
|-
 
| Wednesday 2 June
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Wednesday 2 June
 
| Day
 
|
 
* Canceled
 
|
 
|-
 
| Wednesday 2 June
 
| Swing
 
|
 
* canceled
 
|
 
|-
 
| Thursday 3 June
 
| Owl
 
|
 
* Canceled
 
|
 
|-
 
| Thursday 3 June
 
| Day
 
|
 
* Cooling down target (more likely to start on Swing)
 
* Day shift on standby.
 
|
 
|-
 
| Thursday 3 June
 
| Swing
 
|
 
* Swing shift workers are needed.
 
**PREX detector in counting mode
 
** resume beam in Compton chicane ( MCC )
 
** harp scan for beam profile and beam position ( Shift crew - MCC )
 
** raster check ( Shift crew )
 
** Long down target recovery procedure ( Shift crew )
 
* Alignment checks, Q2 ( Dustin Mc Nulty ).
 
** put sieve in
 
** take alignement data
 
** put sieve out
 
** Q2 measurement
 
** Ask for access to go to integrating mode ( Jon Wexler or Amhed Zafar ) and remove Sieve
 
* Restart Production
 
* Production
 
|
 
|-
 
| Friday 4 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Friday 4 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Friday 4 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Saturday 5 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Saturday 5 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Saturday 5 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Sunday 6 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Sunday 6 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Sunday 6 June
 
| Swing
 
|
 
* Production
 
 
 
|-
 
| Monday 7 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Monday 7 June
 
| Day
 
|
 
* Moller Measurement (noon to 4pm)
 
* Big Change asymmetry run
 
* Production
 
|
 
|-
 
| Monday 7 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Tuesday 8 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Tuesday 8 June
 
| Day
 
|
 
* Production
 
* Wien Flip (9 AM)
 
* Beam study (9-11 AM)
 
|
 
|-
 
| Tuesday 8 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Wednesday 9 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Wednesday 9 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Wednesday 9 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Thursday 10 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Thursday 10 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Thursday 10 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Friday 11 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Friday 11 June
 
| Day
 
|
 
* Production
 
* Wien flip
 
|
 
|-
 
| Friday 11 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Saturday 12 June
 
| Owl
 
|
 
* High Statistics Lead Inelastics, Qsq|GEM test, Calibration of the cavities with the amplifier
 
| all done
 
|-
 
| Saturday 12 June
 
| Day
 
|
 
* Backgrounds: Dipole Scan, Transverse Polarization Measurements.
 
| Finished left dipole scan, right dipole scan is pending
 
|-
 
| Saturday 12 June
 
| Swing
 
|
 
* Transverse Polarization Measurements. Carbon
 
|
 
|-
 
| Sunday 13 June
 
| Owl
 
|
 
* Transverse Polarization Measurements. Lead
 
|
 
|-
 
| Sunday 13 June
 
| Day
 
|
 
* Transverse Polarization Measurements. Lead
 
4494 32k (beam current stepping up, might not be good)
 
4495 78k
 
4496 73k
 
4497
 
| Already took 580K multiplets, 60K of them may not be good data
 
|-
 
| Sunday 13 June
 
| Swing
 
|
 
 
 
* If right Q2 fixed, take 100K more A_T data then go back to production. Otherwise go back to single arm production
 
|
 
|-
 
| Monday 14 June
 
| Owl
 
|
 
* Continue Transverse Polarization Measurements. Blinded tube test
 
|
 
|-
 
| Monday 14 June
 
| Day
 
|
 
* Production
 
|
 
Remaining [https://prex.jlab.org/wiki/index.php/User_talk:Jixie_Zhang auxiliary measurements]  
 
* PREx det. current calibrations (Monday swing)
 
* Finish dipole scan (Tuesday owl)
 
* Oversampling by 2 at 120 Hz (put off/cancelled)
 
* Beam induced linearity studies (put off/cancelled)
 
* Q2 measurements (relative using T5 during dipole scan)
 
* MOLLER commissioning (if can't do anything else - need repair? - see Jixie or Roman)
 
|-
 
| Monday 14 June
 
| Swing
 
|
 
* Production
 
* PREx det. current calibrations (Partially done)
 
|
 
* large charge asymmetry run couldn't be done b/c MCC couldn't set RHWP to 2500 (see [http://www.jlab.org/~adaq/halog/html/1006_archive/100614223155.html Rupesh' log entry])
 
|-
 
| Tuesday 15 June
 
| Owl
 
|
 
* Production
 
* Finish dipole scan (Done)
 
|
 
* Modified dipole scan completed overnight (see Bob's entries [http://www.jlab.org/~adaq/halog/html/1006_archive/100615031427.html 1] and [http://www.jlab.org/~adaq/halog/html/1006_archive/100615050141.html 2])
 
|-
 
| Tuesday 15 June
 
| Day
 
|
 
* Beam Studies  <br>
 
expected to deliver beam to Hall A - '''NO AUTOMATIC ACCESS'''
 
* Production
 
|
 
* large charge asymmetry run taken (see [http://www.jlab.org/~adaq/halog/html/1006_archive/100615093424.html run 4574])
 
* Beam was lost during beam studies after all
 
** Megan and Alex went in to check on the Compton
 
** Jixie and Roman did some work on the Moller, including a refill
 
** Jack and Howard worked on the RHRS dipole which had issues
 
|-
 
| Tuesday 15 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Wednesday 16 June
 
| Owl
 
|
 
* Production
 
|
 
* went to single arm running after right dipole power supply trip
 
|-
 
| Wednesday 16 June
 
| Day
 
|
 
* Right arm dipole repairs
 
* Put silicone on target
 
* Production
 
|
 
* Dipole issues unresolved
 
* Silicone helps target [http://www.jlab.org/~adaq/halog/html/1006_archive/100616154402.html vacuum pressure]
 
|-
 
| Wednesday 16 June
 
| Swing
 
|
 
* Begin with PbD#3 - check temperatures
 
** If too high - switch back to PbD#1
 
* Production - single arm running
 
|
 
* Beam not back until ~11pm
 
* Try to do beam recovery before owl starts
 
|-
 
| Thursday 17 June
 
| Owl
 
|
 
* Production (single arm)
 
|
 
|-
 
| Thursday 17 June
 
| Day
 
|
 
* Right dipole repairs
 
* Wien Flip (10am)
 
|
 
* Wien Flip done this morning
 
* Right dipole working for now
 
* Target warm up flashed off N2 ice - target cooling down
 
|-
 
| Thursday 17 June
 
| Swing
 
|
 
* Trouble sending 70 uA beam
 
|
 
* BCMs needed calibration
 
|-
 
| Friday 18 June
 
| Owl
 
|
 
* Production
 
|
 
* 70 uA beam transport established
 
* Problem with RHRS rates discovered (25x smaller than LHRS)
 
|-
 
| Friday 18 June
 
| Day
 
|
 
* Production
 
* End of Run Party 2-4pm in the ResFac Great Room
 
|
 
* RHRS sieve discovered to be partially in; Howard went in and moved it out
 
|-
 
| Friday 18 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Saturday 19 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Saturday 19 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Saturday 19 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Sunday 20 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Sunday 20 June
 
| Day
 
|
 
* Production
 
|
 
|-
 
| Sunday 20 June
 
| Swing
 
|
 
* Production
 
|
 
|-
 
| Monday 21 June
 
| Owl
 
|
 
* Production
 
|
 
|-
 
| Monday 21 June
 
| Day
 
|
 
* Dismantle detectors - see Dustin or Alex
 
|
 
|-
 
| Tuesday 21 June
 
| Day
 
|
 
* Counting house cleaning party beginning at 8am!
 
|
 
|}
 