== Beamline instrumentation calibration == | == Beamline instrumentation calibration == | ||
+ | |||
+ | # <font color="blue">Basic setup</font> <span style="background-color:#F1C40F">0.5 shift</span> Yves R, Ciprian G: | ||
+ | #* No target. | ||
+ | #* 50uA beam current, through Compton (backgrounds on fingers and Compton photon detector). | ||
+ | # <font color="blue">High current with target</font> <span style="background-color:#F1C40F">0.5 shift</span> Ciprian G, Dustin M: | ||
+ | ## Establish 4x4 raster. Insert lead target. | ||
+ | ## Detector and SAM voltages (Dustin M) | ||
+ | # <font color="blue">Beamline instrumentation calibration</font> <span style="background-color:#F1C40F">0.5 shift</span> Caryn P, | ||
+ | ## Current ramp for BPM/BCM calibrations and detector pedestals [[detailed Calibration plan|detailed plan]] | ||
+ | # <font color="blue"> Initial production condition test</font> <span style="background-color:#F1C40F">0.25 shift</span> Caryn P, | ||
+ | ## detector and SAM widths | ||
+ | ## regression sensitivities | ||
+ | ## beam noise and asymmetry check | ||
+ | ## collimator water and thermocouple temperatures, | ||
+ | ## radiation monitors and ion chamber stability | ||
+ | # <font color="blue"> Width studies </font> <span style="background-color:#F1C40F">0.5 shift</span> KK, | ||
+ | ## detector and SAM widths, targets, shutters, etc | ||
+ | ## deinstall shutters at conclusion of test | ||
+ | |||
+ | |||
# Check the following has been performed | # Check the following has been performed | ||
#* 50uA-70uA beam current, through Compton (backgrounds on fingers and Compton photon detector) with no target | #* 50uA-70uA beam current, through Compton (backgrounds on fingers and Compton photon detector) with no target |
Revision as of 09:44, 25 June 2019
Beamline instrumentation calibration
- Basic setup 0.5 shift Yves R, Ciprian G:
- No target.
- 50uA beam current, through Compton (backgrounds on fingers and Compton photon detector).
- High current with target 0.5 shift Ciprian G, Dustin M:
- Establish 4x4 raster. Insert lead target.
- Detector and SAM voltages (Dustin M)
- Beamline instrumentation calibration 0.5 shift Caryn P,
- Current ramp for BPM/BCM calibrations and detector pedestals detailed plan
- Initial production condition test 0.25 shift Caryn P,
- detector and SAM widths
- regression sensitivities
- beam noise and asymmetry check
- collimator water and thermocouple temperatures,
- radiation monitors and ion chamber stability
- Width studies 0.5 shift KK,
- detector and SAM widths, targets, shutters, etc
- deinstall shutters at conclusion of test
- Check the following has been performed
- 50uA-70uA beam current, through Compton (backgrounds on fingers and Compton photon detector) with no target
- Establish 4x4 raster. Insert lead target.
- Set Detector and SAM voltages (Dustin M)
- Basic setup 0.5 shift Yves R, Ciprian G: Check Conditions OK
- collimator water
- thermocouple temperatures
- radiation monitors
- ion chamber stability
- Setup Locks (these are necessary for main detectors and SAM calibration)
- Slow Target Lock on 4A, 4E (jmenu->"slow locks"-> Orbit Locks Expanded View -> HallATGT)
- Fast feedback for HallA on (iocse9)
- If beam is going through Compton, HallAComLock should probably be on
- Should HallAMolLock be on?
- Basic setup 0.5 shift Yves R, Ciprian G: Coordinate
- Should Compton and Moller DAQ be running during calibration?
- Dustin and Devi examining SAMs and Detectors with online analyzer during calibration
- Juan Carlos/Amali/Adam monitor Compton background rates and run the DAQ?
- Calibration Procedure A: with UNSER
- start at 70uA for 1min (scandata1==value in BCM0l02)
- beam off
- wait for 5sec(for unser to equilibrate), take unser pedestal data point for 30sec (scandata1=0)
- beam on at 75uA
- check slow target lock is in position
- check FFB on for HallA
- check no bpms are saturated on iocse9
- wait for 5sec(for unser to equilibrate), take next data point for 1min
- repeat for 65uA,60uA,55uA,50uA,40uA,30uA,20uA,10uA
- Calibration Procedure B: with pre-calibrated Hall BCM (analog upstream bcm)
- start at 70uA for 1min (scandata1==value in BCM0l02)
- change current to 75uA
- check slow target lock is in position
- check FFB on for HallA
- check no bpms are saturated on iocse9
- take next 1min data point
- repeat for 65uA,60uA,55uA,50uA,40uA,30uA,20uA,10uA
- Calibration Procedure C: for BPMs (Compton bpms not yet calibrated)
- at 70uA, set gains off for iocse9,iocse10 (Hall) iocse11,iocse12,iocse19,iocinse4 (Inj)
- rperform Calibration Procedure B with pre-calibrated Hall BCM
- Beamline instrumentation calibration 0.5 shift Caryn P,
- Current ramp for BPM/BCM calibrations and detector pedestals detailed plan
- Initial production condition test 0.25 shift Caryn P,
- detector and SAM widths
- regression sensitivities
- beam noise and asymmetry check
- collimator water and thermocouple temperatures,
- radiation monitors and ion chamber stability
- Width studies 0.5 shift KK,
- detector and SAM widths, targets, shutters, etc
- deinstall shutters at conclusion of test