Line 27: Line 27:
 
#* Need to fix the BCMs (Musson)
 
#* Need to fix the BCMs (Musson)
 
| BPMs fixed, bias left on after study; analog BCM problem from Hall and not fixed; plan is to use digital BCMs with separate receivers
 
| BPMs fixed, bias left on after study; analog BCM problem from Hall and not fixed; plan is to use digital BCMs with separate receivers
|-style="background: #FCF3CF;
+
|-
 
| Swing
 
| Swing
 
|  
 
|  

Revision as of 08:50, 26 July 2019



PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Thursday, July 25 Owl production at 70uA
Day
  1. Planned:
    • production at 70uA
    • ~30 minutes for injector bias tests during Hall C gas work (Caryn)
  2. Unplanned:
    • Access to fix the BPMs/ move away from beamline (Francis)
    • Need to fix the BCMs (Musson)
BPMs fixed, bias left on after study; analog BCM problem from Hall and not fixed; plan is to use digital BCMs with separate receivers
Swing
  1. Beam recovery procedure
  2. production at 70uA
Friday, July 26 Owl production at 70uA deltaT on the collimator increased. Water out temp exceeding our set limits
Day
  1. production at 70uA
  2. Brief access to swap the digital receiver when Musson and Co. ready
  3. Some beam tuning to look at reducing the trip rate
  4. Compton tuning? (laser work needs to be completed)
Swing production at 70uA
Saturday, July 27 Owl production at 70uA
Day production at 70uA
Swing production at 70uA
Sunday, July 28 Owl production at 70uA
Day production at 70uA
Swing production at 70uA
Monday, July 29 Owl production at 70uA
Day production at 70uA
Swing production at 70uA
Tuesday, July 30 Owl production at 70uA
Day production at 70uA
Swing production at 70uA
Wednesday, July 31 Owl production at 70uA
Day production at 70uA
Swing production at 70uA

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting