Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchLine 44: | Line 44: | ||
# Brief access to swap the digital receiver when Musson and Co. ready | # Brief access to swap the digital receiver when Musson and Co. ready | ||
# Some beam tuning to look at reducing the trip rate | # Some beam tuning to look at reducing the trip rate | ||
− | |||
| | | | ||
|-style="background: #FCF3CF; | |-style="background: #FCF3CF; | ||
Line 83: | Line 82: | ||
|- | |- | ||
| Day | | Day | ||
− | |production at 70uA | + | | |
+ | # production at 70uA | ||
+ | # Compton tuning? (laser work needs to be completed) | ||
| | | | ||
|- | |- |
Revision as of 08:51, 26 July 2019
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Thursday, July 25 | Owl | production at 70uA | |
Day |
|
BPMs fixed, bias left on after study; analog BCM problem from Hall and not fixed; plan is to use digital BCMs with separate receivers | |
Swing |
|
||
Friday, July 26 | Owl | production at 70uA | deltaT on the collimator increased. Water out temp exceeding our set limits |
Day |
|
||
Swing | production at 70uA | ||
Saturday, July 27 | Owl | production at 70uA | |
Day | production at 70uA | ||
Swing | production at 70uA | ||
Sunday, July 28 | Owl | production at 70uA | |
Day | production at 70uA | ||
Swing | production at 70uA | ||
Monday, July 29 | Owl | production at 70uA | |
Day |
|
||
Swing | production at 70uA | ||
Tuesday, July 30 | Owl | production at 70uA | |
Day | production at 70uA | ||
Swing | production at 70uA | ||
Wednesday, July 31 | Owl | production at 70uA | |
Day | production at 70uA | ||
Swing | production at 70uA |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting