Line 12: Line 12:
 
|-  
 
|-  
 
! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
 
! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
|-
 
| rowspan="3" | Tuesday, July 30
 
|Owl
 
|low current running beginning at 8am (if approved)
 
|
 
|-
 
| Day
 
| Target fix
 
|
 
|-
 
| Swing
 
|
 
* Tests with no target
 
# collimator centering angles with tune beam
 
# BCM calibrations
 
# BPM calibrations
 
# position feedback study
 
|
 
|-
 
| rowspan="3" | Wednesday, July 31
 
|Owl
 
|production at 70uA
 
|
 
|-
 
| Day
 
|
 
# HRS quad repairs
 
# target repairs
 
# Compton work
 
# BCM repair
 
|
 
# HRS quad repairs - both operational; nothing really done to right
 
# target repairs - mechanical work done, modifying software for new setpoints
 
# Compton work ongoing
 
# 2nd one working as well as we can tell
 
|-
 
| Swing
 
|
 
# Raster check
 
# Detector alignment (low current)
 
#* Main detectors
 
#* AT detectors
 
# BCM test and Current and Pita scans
 
# production at 70uA
 
|
 
|-
 
| rowspan="3" | Thursday, August 1
 
| Owl
 
| production at 70uA
 
|
 
|-
 
| Day
 
| production at 70uA
 
|
 
|-
 
| Swing
 
| Production running at 70uA
 
|
 
 
|-
 
|-
 
| rowspan="3" | Friday, August 2
 
| rowspan="3" | Friday, August 2

Revision as of 15:12, 7 August 2019



PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Friday, August 2 Owl Production running at 70uA
Day
  1. Wien flip starting at 8:30am
  2. Compton work in the hall: lens, mode-matching, PPLN tuning
  3. Production 70uA; (IHWP OUT, start slug 26)
raster changed to 4 x 5 mm2 for slug 26
Swing Production running at 70uA
Saturday, August 3 Owl Production running at 70uA
Day
  1. Address issues-- Col. temps, and increased det. widths
  2. Production running at 70uA
changed to Pb9 target
Swing Production running at 70uA
Sunday, August 4 Owl Production running at 70uA
Day Moller starting at 8am
Swing more Moller
Monday, August 5 Owl more Moller
Day
  1. Compton work in Hall
  2. Production running at 70uA
Swing Production running at 70uA
Tuesday, August 6 Owl Production running at 70uA
Day
  1. Production until 10:30 am
  2. Controlled access for Compton work
Swing Production running at 70uA
Wednesday, August 7 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA
Thursday, August 8 Owl Production running at 70uA
Day
  1. Production running at 70uA
  2. Compton Chicane tuning; Moller solenoid axis and lock
Swing Production running at 70uA
Friday, August 9 Owl Production running at 70uA
Day Production running at 70uA
Swing Production running at 70uA

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting