Difference between revisions of "RunPlanDaily CREX"

From PREX Wiki
Jump to navigationJump to search
Line 11: Line 11:
 
|-  
 
|-  
 
! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Comments/Status
 
! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Comments/Status
|-
 
| rowspan="3" | Friday, December 13
 
| Owl
 
| high-current commissioning
 
|
 
|-
 
| Day
 
| Spin dance cancelled; production when have beam
 
|
 
|-
 
| Swing
 
| high-current commissioning/pre-production
 
| Goal is to get the beamline instrumentation ready for PQB to get a look at regression and widths, etc. (pre-production)
 
 
|-
 
|-
 
| rowspan="3" | Saturday, December 14
 
| rowspan="3" | Saturday, December 14

Revision as of 16:49, 15 December 2019



CREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Comments/Status
Saturday, December 14 Owl Production
Day Production, detector alignment check, change IHWP, check target pressure with large raster
Swing Production
Sunday, December 15 Owl Production
Day Production
Swing Production Possibly do optics?
Monday, December 16 Owl Production
Day Production
Swing Production
Tuesday, December 17 Owl Production
Day No beam if we have good running over weekend and Hall C is ready
Swing
Wednesday, December 18 Owl
Day
Swing
Friday, December 20 Owl
Day
Swing

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting