== Daily Run Plan ==
 
  
Here are details of the daily run plan.  See also the global [https://prex.jlab.org/wiki/index.php?title=RunPlan Run Plan]The person responsible should ensure that
+
<br><br>
a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator
+
[[Main_Page|<B>CREX Main</B>]] << [[Main_Page_PREXII|PREX II Main]] << [[Run Coordinator Tools]] <br><br>
as the situation on the ground changes.  
+
 
<hr>
+
[[PREX2RunPlan2019 | PREX Global Run Plan]] -- [[RunPlanDaily_CREX|CREX Daily Run Plan]]
 +
 
 +
== Current Daily Run Plans ==
 +
 
 +
The current day is indicated by a color.
 +
 
 +
{| class="wikitable" border="1" style="width:100%; text-align:left;border-collapse:collapse"
 +
|-
 +
! style="width:10%"| Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
  
{| border="1"
 
|+ Daily Run Plan for PREX &nbsp; (latest at bottom)
 
! Date (2010) !! Shift !!---------- Activity (Responsible) ----------!!---&nbsp;Status&nbsp;---
 
 
|-
 
|-
| 03/19
+
| rowspan="3" | Wedsday, September 4
| day
+
| Owl
| pump down; Møller, Compton, septum install; Q2 repair<br />
+
| Production 71uA
Insert sieve. (Techs)
+
|
 +
|-
 +
| Day
 +
| Moller
 +
|
 +
|-
 +
| Swing
 +
| Moller
 +
|
 +
|-
 +
| rowspan="3" | Thursday, September 5
 +
| Owl
 +
| Production 71uA
 +
|
 +
|-
 +
| Day
 +
| Mott polarimetry measurements
 +
|
 +
|-
 +
| Swing
 +
| Production 71uA
 
|
 
|
 
|-
 
|-
| 03/19
+
| rowspan="3" | Friday, September 6
| swing
+
| Owl
| Beam restore (B-team)
+
| Production 71uA
| done
+
|
 
|-
 
|-
| 03/20
+
| Day
| owl
+
| Production 85uA
 
|  
 
|  
* <font color="red">Septum checkout (Michaels: Page when beam imminent & spectrometer ready)</font>
 
also:
 
* Initial look at low current cavity monitors (Zafar: Page when beam imminent & spectrometer ready)
 
* Target alignment (Michaels)
 
* VDC checkout (Michaels)
 
* Quartz detectors checkout (McNulty, Wexler -- page when VDC tracks seen)
 
* GEM checkout (Camsonne -- page when VDC tracks seen, if left dipole is operating)
 
----
 
All at 1-2 µA.<br />
 
Scattered energy ~ beam energy = 1.063 GeV.<br />
 
Quad settings:
 
*Right arm:
 
** Q1: dI/dP= 411.2474 Amps/GeV/c
 
** Q2: dI/dP= 436.2014 Amps/GeV/c
 
** Q3: dI/dP= 433.3897 Amps/GeV/c
 
* Left Arm:
 
** Q1: dI/dP= 419.8772 Amps/GeV/c
 
** Q2: dI/dP= 435.6273 Amps/GeV/c
 
** Q3: dI/dP= 434.9682 Amps/GeV/c
 
"Usual" polarity
 
| done
 
 
|-
 
|-
| 03/20
+
| Swing
| day
+
| Production 85uA
| Beam off & hall open 9:00 am<br />
+
|
Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs)
+
|-
| done
+
| rowspan="3" | Saturday, September 7
 +
| Owl
 +
| Production 85uA
 +
|
 
|-
 
|-
| 03/20
+
| Day
| swing
+
| Production 85uA
 
|  
 
|  
* Close up hall
 
* Benesch tuning (1/2 - 2 hours)
 
* Verify quad polarities (Camsonne)
 
* Cavity monitors basic function test (Zafar)
 
* <font color="red">Low current cavity monitors setup (Musson, Zafar)</font> (2 hours)
 
| in progress
 
 
|-
 
|-
| 3/21
+
| Swing
| owl
+
| Production 85uA
 
|
 
|
* Access for GEM installation (Camsonne)
 
* Remove sieves (assuming low current cavities working)
 
* <font color="red">Spectrometer checkout:</font>
 
** Quartz detectors checkout (McNulty)
 
** Lumi checkout (Mercado) (2 µA on Ta)
 
** GEM checkout (Camsonne?)
 
----
 
At <~ 100 nA up to few µA.
 
| not done
 
 
|-
 
|-
| 3/21
+
|-style="background: #FCF3CF;
| day
+
| rowspan="3" | Sunday, September 8
 +
| Owl
 +
| Production 85uA
 
|
 
|
* Put in water cell
+
|-
* <font color="red">Pointing measurement</font>
+
| Day
* A_T hole?
+
| Moller Polarimetry
----
+
|
Page Jack Segal if long access.
+
|-
| not done
+
| Swing
 +
| Q2 measurement and Spectrometer rescattering
 +
| https://prex.jlab.org/wiki/index.php/RescatteringPlan
 +
|-
 +
| rowspan="3" | Monday, September 9
 +
| Owl
 +
| Production 85uA
 +
|
 +
|-
 +
| Day
 +
| SADness
 +
| Scheduled Accelerator Down begins
 
|}
 
|}
 +
[[Run plan history | <B>Previous Daily Run Plans</B>]]
 +
 +
== Instructions for RC ==
 +
 +
* Let the day shift know what to do while you attend the MCC meeting
 +
* Copy the daily run plans for the previous week to the [[Run plan history]]
 +
* Copy the [[Run Plan Template]] table to this page and change the dates
 +
* Update the plan above (if necessary) after the MCC meeting
 +
 +
[[Category:HOW TO]] [[Category:SL]] [[Category:RC]]
 +
 +
<hr>

Latest revision as of 16:22, 5 December 2019



CREX Main << PREX II Main << Run Coordinator Tools

PREX Global Run Plan -- CREX Daily Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Wedsday, September 4 Owl Production 71uA
Day Moller
Swing Moller
Thursday, September 5 Owl Production 71uA
Day Mott polarimetry measurements
Swing Production 71uA
Friday, September 6 Owl Production 71uA
Day Production 85uA
Swing Production 85uA
Saturday, September 7 Owl Production 85uA
Day Production 85uA
Swing Production 85uA
Sunday, September 8 Owl Production 85uA
Day Moller Polarimetry
Swing Q2 measurement and Spectrometer rescattering https://prex.jlab.org/wiki/index.php/RescatteringPlan
Monday, September 9 Owl Production 85uA
Day SADness Scheduled Accelerator Down begins

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting