== Daily Run Plan ==
 
  
Here are details of the daily run plan.  See also the [https://prex.jlab.org/wiki/index.php?title=RunPlan Global Run Plan]The person responsible should ensure that
+
<br><br>
a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator
+
[[Main_Page|<B>CREX Main</B>]] << [[Main_Page_PREXII|PREX II Main]] << [[Run Coordinator Tools]] <br><br>
as the situation on the ground changes.  
+
 
<hr>
+
[[PREX2RunPlan2019 | PREX Global Run Plan]] -- [[RunPlanDaily_CREX|CREX Daily Run Plan]]
 +
 
 +
== Current Daily Run Plans ==
 +
 
 +
The current day is indicated by a color.
 +
 
 +
{| class="wikitable" border="1" style="width:100%; text-align:left;border-collapse:collapse"
 +
|-
 +
! style="width:10%"| Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
  
{| border="1"
 
|+ Daily Run Plan for PREX &nbsp; (latest at bottom)
 
! Date (2010) !! Shift !!---------- Activity (Responsible) ----------!!---&nbsp;Status&nbsp;---
 
|-
 
| 03/19
 
| Day
 
| pump down; Møller, Compton, septum install; Q2 repair<br />
 
Insert sieve. (Techs)
 
|done
 
|-
 
| 03/19
 
| Swing
 
| Beam restore (B-team)
 
| done
 
|-
 
| 03/20
 
| Owl
 
|
 
* <font color="red">Septum checkout (Michaels: Page when beam imminent & spectrometer ready)</font>
 
also:
 
* Initial look at low current cavity monitors (Zafar: Page when beam imminent & spectrometer ready)
 
* Target alignment (Michaels)
 
* VDC checkout (Michaels)
 
* Quartz detectors checkout (McNulty, Wexler -- page when VDC tracks seen)
 
* GEM checkout (Camsonne -- page when VDC tracks seen, if left dipole is operating)
 
| done
 
----
 
All at 1-2 µA.<br />
 
Scattered energy ~ beam energy = 1.063 GeV.<br />
 
Quad settings:
 
*Right arm:
 
** Q1: dI/dP= 411.2474 Amps/GeV/c
 
** Q2: dI/dP= 436.2014 Amps/GeV/c
 
** Q3: dI/dP= 433.3897 Amps/GeV/c
 
* Left Arm:
 
** Q1: dI/dP= 419.8772 Amps/GeV/c
 
** Q2: dI/dP= 435.6273 Amps/GeV/c
 
** Q3: dI/dP= 434.9682 Amps/GeV/c
 
"Usual" polarity
 
|-
 
| 03/20
 
| Day
 
| Beam off & hall open 9:00 am<br />
 
Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs)
 
| done
 
|-
 
| 03/20
 
| Swing
 
|
 
* Close up hall
 
* Benesch tuning (1/2 - 2 hours)
 
* Verify quad polarities (Camsonne)
 
* Cavity monitors basic function test (Zafar)
 
* <font color="red">Low current cavity monitors setup (Musson, Zafar)</font>
 
| done
 
|-
 
| 3/21
 
| Owl
 
|
 
* <font color="red">Low current cavity monitors setup (Musson, Zafar)</font>
 
* Access for GEM installation (Camsonne)
 
| done but GEMs not ready
 
|-
 
| 3/21
 
| Day
 
|
 
* <font color="red">Spectrometer checkout:</font>
 
** Quartz detectors checkout (McNulty, Wexler)
 
** Lumi checkout (Mercado) (2 µA on Ta)
 
** GEM checkout (Camsonne?)
 
* A line tuning (Benesch)
 
* Raster checkout
 
* Access:
 
** Low current cavities
 
** Target position
 
** Quartz
 
** Scintillator alignment
 
** LQ2
 
| done
 
|-
 
| 3/21
 
| Swing
 
|
 
* <font color="red">Low current cavity monitors setup (Michaels, Zafar)</font>
 
* Remove sieves
 
* Initial look at sieve out data
 
* Replace sieves
 
| done
 
|-
 
| 3/22
 
| Owl
 
|
 
* <font color="red">Pointing measurement (Riordan)</font>
 
* Remove sieves
 
* Repeat pointing measurements with no sieves
 
* If done or unable to continue before 4 am page Luis Mercado to do lumi checks
 
* After 4 am page Dustin McNulty for detector work
 
|done
 
|-
 
| 3/22
 
| Day
 
| <font color="red">
 
* Optics (Liyanage)</font>Sieve OUT.  NB Current limit 2 uA!
 
|done
 
 
|-
 
|-
| 3/22
+
| rowspan="3" | Wedsday, September 4
| Swing
 
|
 
* Optics continued, sieve IN.  NB Current limit 2 uA! (Shift Crew)
 
|done
 
|-
 
| 3/23
 
 
| Owl
 
| Owl
 +
| Production 71uA
 
|
 
|
* Quartz detectors resolution studies (KK, Dustin, John W)
 
* Lumi studies (Luis)
 
|done
 
 
|-
 
|-
| 3/23
 
 
| Day
 
| Day
 +
| Moller
 
|  
 
|  
* Remove water target. (Target, Techs)
 
* Reconfigure Moller cryo.
 
* '''Beam studies''' ~ 2pm, study of helicity correlated position differences for spin flipper states. (Dalton, Rupesh, Reza)
 
|water cell removed, rest not finished
 
 
|-
 
|-
| 3/23
 
 
| Swing
 
| Swing
 +
| Moller
 
|
 
|
* Target pumpdown
 
|done
 
 
|-
 
|-
| 3/24
+
| rowspan="3" | Thursday, September 5
 
| Owl
 
| Owl
 +
| Production 71uA
 
|
 
|
* Target pumpdown
 
|done
 
 
|-
 
|-
| 3/24
 
 
| Day
 
| Day
 +
| Mott polarimetry measurements
 
|  
 
|  
* Target cooldown
 
|done
 
 
|-
 
|-
| 3/24
 
 
| Swing
 
| Swing
 +
| Production 71uA
 
|
 
|
* Tune high current beam into Hall A
 
|done
 
 
|-
 
|-
| 3/25
+
| rowspan="3" | Friday, September 6
 
| Owl
 
| Owl
 +
| Production 71uA
 
|
 
|
* Commission lead target, 50 uA (Bob)
 
* Lumis and oversampling tests (KK, Luis, Paul)
 
|in progress
 
 
|-
 
|-
| 3/25
 
 
| Day
 
| Day
 +
| Production 85uA
 
|  
 
|  
* Access to fix left dipole
 
|done
 
 
|-
 
|-
| 3/25
 
 
| Swing
 
| Swing
 +
| Production 85uA
 
|
 
|
* Parity Quality commissioning (Kent, Rupesh, Luis, Dustin)
 
* Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng)
 
|postponed
 
 
|-
 
|-
| 3/26
+
| rowspan="3" | Saturday, September 7
 
| Owl
 
| Owl
 +
| Production 85uA
 
|
 
|
* High Luminosity Detector Commissioning
 
|in progress
 
 
|-
 
|-
| 3/26
 
 
| Day
 
| Day
 +
| Production 85uA
 
|  
 
|  
*Moller Checkout
 
|postponed
 
 
|-
 
|-
| 3/26
 
 
| Swing
 
| Swing
 +
| Production 85uA
 
|
 
|
*High Current on C12 (thick and thin)
 
|partly done
 
 
|-
 
|-
| 3/27
+
|-style="background: #FCF3CF;
 +
| rowspan="3" | Sunday, September 8
 
| Owl
 
| Owl
 +
| Production 85uA
 
|
 
|
| no beam
 
 
|-
 
|-
| 3/27
 
 
| Day
 
| Day
 +
| Moller Polarimetry
 
|  
 
|  
| no beam
 
|-
 
| 3/27
 
| Swing
 
|
 
*High-current on thick C12, adjust HV (Luis or Bob)
 
*Finish the commissioning of thick Pb target (Bob, Ahmed)
 
*Electronic Commissioning (KK, Luis, Paul, Jon et al)
 
|done, high-current tests continue
 
|-
 
| 3/28
 
| Owl
 
|
 
*Continue with the above, if necessary.
 
*High Luminosity Commissioning (Rupesh, Luis, Jon, Bob)
 
*BCM/BPM calibration (Rupesh)
 
*Establishing Parity Measurements, Charge feedback, blinding (Rupesh, Jon)
 
|not finished
 
|-
 
| 3/28
 
| Day
 
|
 
*Comparison Study of Optics Tunes (Seamus, Nilanga, Kiad)
 
*Sometime before Monday, submit the ATLIS plan for Dithering test (Rupesh)
 
|done
 
|-
 
| 3/28
 
| Swing
 
|
 
*Continue Optics if necessary.
 
*Continue High Luminosity Commissioning
 
|done
 
|-
 
| 3/29
 
| Owl
 
|
 
*Mini-production run (shift crew)
 
*Stop beam at 07:00 or whenever Ed Folts asks to.
 
|done
 
|-
 
| 3/29
 
| Day
 
|
 
*Open Hall A to set up Moller and Compton (Ed Folts, Sasha, Sirish, et.al.)
 
*Work on GEMs (Alex, Seamus, et.al.)
 
*MCC to do beam studies while Hall A open
 
*Detector linearity/LED tests (Luis)
 
*Setup WAC analysis (Mark, Mindy)
 
|done
 
|-
 
| 3/29
 
| Swing
 
|
 
*Moller magnet cooldown
 
*Optics and acceptance studies (Seamus, Ahmed, Nilanga)
 
|done
 
|-
 
| 3/30
 
| Owl
 
|
 
*Commission charge feedback (Mark)
 
*Current monitor calibration and pedestals determination (Mark)
 
*Quasi-production on Empty Target (owl shift crew)
 
|done
 
|-
 
| 3/30
 
| Day
 
|
 
*Access do work on Moller and Compton.
 
*Some GEM installation work. (Alex, Seamus, Kiad, Nilanga)
 
*Possible linearity/LED study. (Luis)
 
|done, except linearity
 
|-
 
| 3/30
 
| Swing
 
|
 
*First Commissioning of Moller -- Beam Checks (Sasha, Javier, Roman, Jay)
 
|done
 
|-
 
| 3/31
 
| Owl
 
|
 
*Scans of Septum and quad Q1 for tunes A and B. (Bob)
 
*Beam Studies of Helicity Correlations
 
|done
 
|-
 
| 3/31
 
| Day
 
|
 
*Beam Tuning (Jay Benesch)
 
|done
 
|-
 
| 3/31
 
| Swing
 
|
 
*Either or both of these:
 
* a) Moller Commissioning (Sasha, Javier, Roman, Jay)
 
* b) Tests of Dithering and other Beam-Related things (Kent, Rupesh)
 
|Moller was done
 
|-
 
| 4/1
 
| Owl
 
|
 
*If Kent's tests not done on Swing, continue here. (Kent, Rupesh)
 
*Beam and Septum scan with new tune (Seamus)
 
*Helicity-correlated beam studies (Shift crew)
 
|done
 
|-
 
| 4/1
 
| Day
 
|
 
* Beam Tuning (Jay)
 
|done, successful
 
|-
 
| 4/1
 
| Swing
 
|
 
* More beam tuning if necessary
 
* Moller Commissioning
 
|done
 
|-
 
| Friday 2 April
 
| Owl
 
|
 
*Assuming the HRS tune has been frozen
 
*Check detector alignment
 
*A_T studies
 
*Q<sup>2</sup> Measurements
 
|partly done, needs more work
 
|-
 
| Friday 2 April
 
| Day
 
|
 
*Tuning Beam for Compton
 
|done
 
|-
 
| Friday 2 April
 
| Swing
 
|
 
*  20:00 Obtain sieve runs (optics mini-run plan), Q<sup>2</sup> measurements (Bob)
 
|done, but not Q<sup>2</sup>
 
|-
 
| Saturday 3 April
 
| Owl
 
|
 
* Obtain sieve runs on Ta (Nilanga mini-run plan)
 
* Put in Lead target at low current and do counting-mode runs (Rupesh, Ahmed)
 
* Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
 
|done
 
|-
 
| Saturday 3 April
 
| Day
 
|
 
* Moller Commissioning <font color="green">(priority activity)</font>
 
* Work on getting into production mode (Mark, Rupesh)
 
|done, but not yet in prod.
 
 
|-
 
|-
| Saturday 3 April
 
 
| Swing
 
| Swing
|  
+
| Q2 measurement and Spectrometer rescattering
* Moller commissioning
+
| https://prex.jlab.org/wiki/index.php/RescatteringPlan
|done
 
 
|-
 
|-
| Sunday 4 April
+
| rowspan="3" | Monday, September 9
 
| Owl
 
| Owl
 +
| Production 85uA
 
|
 
|
* Counting data on tune Y (right arm) super-thin carbon
 
* Change to tune B
 
* Integrate-mode with Lead at 2 or 3 uA (Luis, Jon)
 
|done
 
 
|-
 
|-
| Sunday 4 April
 
 
| Day
 
| Day
|
+
| SADness
* Integrate-mode with thick carbon 50 uA
+
| Scheduled Accelerator Down begins
* Compton QWP1 calibration.
 
|done
 
|-
 
| Sunday 4 April
 
| Swing
 
|
 
* General Compton commissioning and pseudo-production (empty target) parity data at 50 uA.
 
|done
 
|-
 
| Monday 5 April
 
| Owl
 
|
 
* pseudo-production (empty target) parity data and Compton data at 50 uA.
 
|done
 
|-
 
| Monday 5 April
 
| Day
 
|
 
* 12:00 Jay to run optics test (~ 30 mins)
 
* Moller Spin Dance
 
* Set up vertical polarization and measure A_T
 
|done
 
|-
 
| Monday 5 April
 
| Swing
 
|
 
*Continue to setup up vertical polarization
 
*Measurements of A_T on Pb and C12
 
|done
 
|-
 
| Tuesday 6 April
 
| Owl
 
|
 
* Continue measurements of A_T on Pb and C12
 
|partly done
 
|-
 
| Tuesday 6 April
 
| Day
 
|
 
* Possible horizontal scan:  Tune B with sieve slit (Seamus)
 
* When ready: Relocate Quartz Detectors (Dustin, Jack)
 
|postponed: vacuum problems
 
|-
 
| Tuesday 6 April
 
| Swing
 
|
 
* In restricted access.
 
* Any activities that require access.
 
* Shift canceled
 
|
 
|-
 
| Wednesday 7 April
 
| Owl
 
|
 
* Shift cancelled
 
|
 
|-
 
| Wednesday 7 April
 
| Day
 
|
 
*Shift cancelled
 
* Investigate target vacuum problem
 
* Move quartz detectors (Dustin, Jack)
 
|Leak found at O-ring connection between target chamber and collimator box
 
|-
 
| Wednesday 7 April
 
| Swing
 
|
 
*Shift cancelled
 
|-
 
| Thursday 8 April
 
| Owl
 
|
 
*Shift cancelled
 
|-
 
| Thursday 8 April
 
| Day
 
|
 
*Shift cancelled
 
|Target chamber open, found that the 4th foil in Optics target blown off
 
|-
 
| Thursday 8 April
 
| Swing
 
|
 
*Shift cancelled
 
|
 
|-
 
| Friday 9 April
 
| Owl
 
|
 
*Shift cancelled
 
|
 
|-
 
| Friday 9 April
 
| Day
 
|
 
* To be determined.
 
* When ready: Install GEMs
 
|
 
|-
 
| Friday 9 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Saturday 10 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Saturday 10 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Saturday 10 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Sunday 11 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Sunday 11 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Sunday 11 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Monday 12 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Monday 12 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Monday 12 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Tuesday 13 April
 
| Owl
 
|
 
* Cancelled
 
|
 
|-
 
| Tuesday 13 April
 
| Day
 
|
 
* Cancelled
 
|
 
|-
 
| Tuesday 13 April
 
| Swing
 
|
 
* Cancelled
 
|
 
|-
 
| Wednesday 14 April
 
| Owl
 
|
 
* Cancelled
 
* When we resume we may need to re-check alignment (scans of sieve slit and target position).
 
* If sieves were moved during the vacuum repair we may need to do the water cell angle measurement.
 
* Eventually we check the alignment of the quartz detectors and get back into production.
 
* Plus a generous amount of time for Moller and Compton Commissioning.
 
| Techs are working on vacuum repair.  Earliest optimistic startup is Thursday Day.  Likely later
 
 
|}
 
|}
 +
[[Run plan history | <B>Previous Daily Run Plans</B>]]
 +
 +
== Instructions for RC ==
 +
 +
* Let the day shift know what to do while you attend the MCC meeting
 +
* Copy the daily run plans for the previous week to the [[Run plan history]]
 +
* Copy the [[Run Plan Template]] table to this page and change the dates
 +
* Update the plan above (if necessary) after the MCC meeting
 +
 +
[[Category:HOW TO]] [[Category:SL]] [[Category:RC]]
 +
 +
<hr>

Latest revision as of 16:22, 5 December 2019



CREX Main << PREX II Main << Run Coordinator Tools

PREX Global Run Plan -- CREX Daily Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Wedsday, September 4 Owl Production 71uA
Day Moller
Swing Moller
Thursday, September 5 Owl Production 71uA
Day Mott polarimetry measurements
Swing Production 71uA
Friday, September 6 Owl Production 71uA
Day Production 85uA
Swing Production 85uA
Saturday, September 7 Owl Production 85uA
Day Production 85uA
Swing Production 85uA
Sunday, September 8 Owl Production 85uA
Day Moller Polarimetry
Swing Q2 measurement and Spectrometer rescattering https://prex.jlab.org/wiki/index.php/RescatteringPlan
Monday, September 9 Owl Production 85uA
Day SADness Scheduled Accelerator Down begins

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting