*Dustin: The frame for main detector is ready to go. But cann't put anything there unless the UVa GEM is ready. | *Dustin: The frame for main detector is ready to go. But cann't put anything there unless the UVa GEM is ready. | ||
− | *Chandan: Devi is working | + | *Chandan: Devi is working on S3 mount design. |
− | *Dustin: We need Z- | + | *Dustin: We need Z-positions and transverse positions of the AT detectors. |
− | **Seamus: Ryan is supposed to give those | + | **Seamus: Ryan is supposed to give those dimensions. |
*Dustin: By next weekend, we expect to be ready with RHRS. | *Dustin: By next weekend, we expect to be ready with RHRS. | ||
− | *Chandan: | + | *Chandan: There was good progress on counting DAQ work. |
− | *Chandan: We | + | *Chandan: We are planning to take cosmic data using VDC in this weekend. |
*Siyu: One GEM detector is already moved inside the Hall. Working on cable mounting. The detector will be mounted on hut on Monday. | *Siyu: One GEM detector is already moved inside the Hall. Working on cable mounting. The detector will be mounted on hut on Monday. | ||
Line 24: | Line 24: | ||
Dustin, Seamus, Chandan, Ryan, Siyu, Ye Tian | Dustin, Seamus, Chandan, Ryan, Siyu, Ye Tian | ||
===Excused=== | ===Excused=== | ||
+ | Devi |
Latest revision as of 22:39, 10 May 2019
Back to Main Page >> GEM_Meeting
Logistic information
BlueJeans calling instructions: Toll-Free Number (U.S.& Canada): 888-240-2560 International toll number: 408-740-7256 Bluejeans CODE: 998 903 0149 Bluejeans link: https://bluejeans.com/9989030149
Agenda
Minutes
- Dustin: The frame for main detector is ready to go. But cann't put anything there unless the UVa GEM is ready.
- Chandan: Devi is working on S3 mount design.
- Dustin: We need Z-positions and transverse positions of the AT detectors.
- Seamus: Ryan is supposed to give those dimensions.
- Dustin: By next weekend, we expect to be ready with RHRS.
- Chandan: There was good progress on counting DAQ work.
- Chandan: We are planning to take cosmic data using VDC in this weekend.
- Siyu: One GEM detector is already moved inside the Hall. Working on cable mounting. The detector will be mounted on hut on Monday.
Present
Dustin, Seamus, Chandan, Ryan, Siyu, Ye Tian
Excused
Devi