* [[DAQ_Testing/20190628|DAQ Testing - June 28th, 2019]] - Raster calibration | * [[DAQ_Testing/20190628|DAQ Testing - June 28th, 2019]] - Raster calibration | ||
* [[DAQ_Testing/20190630|DAQ Testing - June 30th, 2019]] - running the parity DAQ with Lead to see Main detectors pickup the helicity flip | * [[DAQ_Testing/20190630|DAQ Testing - June 30th, 2019]] - running the parity DAQ with Lead to see Main detectors pickup the helicity flip | ||
+ | * [[DAQ_Testing/20190714|DAQ Testing - July 14th, 2019]] - DAQ TS issues, skipping events and eventual HRS DAQ adding helicity and TS replacement | ||
* [[DAQ_Testing/20190729|DAQ Testing - July 29th, 2019]] - Testing with tune beam - DAQ bandwidth | * [[DAQ_Testing/20190729|DAQ Testing - July 29th, 2019]] - Testing with tune beam - DAQ bandwidth | ||
* [[DAQ_Testing/20190807|DAQ Testing - August 7th, 2019]] - 240 Hz update, fixing /tmp/ overflow, and raster synch update for 240 Hz (primary goal is to get raster to work properly) | * [[DAQ_Testing/20190807|DAQ Testing - August 7th, 2019]] - 240 Hz update, fixing /tmp/ overflow, and raster synch update for 240 Hz (primary goal is to get raster to work properly) |
Latest revision as of 15:02, 24 September 2019
Further information is available in DAQ Documentation Portal and DAQ Testing Portal, see also the Run List
Summer 2018 Resurrection
See the DAQ Meeting List, in particular May, June and July 2018 notes from Cameron and Chandan's visit with Bob, for details on efforts to resurrect the Parity DAQ system and run everything under Trigger Supervisor (TS) control.
Summer 2018 Recommissioning
Cameron and Chandan returned to JLab in late July 2018 to work with Bob on testing all ADC channels and other hardware and software, to ensure dynamic range and functionality, as well as updating things and maintaining usability for all interested parties.
Testing ADC Channels
See also - DAQ Layouts
Automating Testing/Analysis Software
See also - DAQ Software
Notes on specific module testing
See also - DAQ Hardware
- DAQ Testing - July 27th, 2018
- DAQ Testing - July 28th, 2018
- DAQ Testing - July 29th, 2018
- DAQ Testing - July 30th, 2018
- DAQ Testing - July 31st, 2018
- DAQ Testing - August 1st, 2018
- DAQ Testing - August 2nd, 2018
- DAQ Testing - August 3rd, 2018
- DAQ Testing - September 10th, 2018
- DAQ Testing - November 1st, 2018
- DAQ Testing - November 2nd, 2018 - Reading out scalers with EPICs server - ET deadtime tests - some timing diagram notes
- DAQ Testing - November 5th, 2018 - ET deadtime tests - Carl Timmer suggests monitorGui
- DAQ Testing - November 6th, 2018
- DAQ Testing - November 11th, 2018
- DAQ Testing - November 14th, 2018
- DAQ Testing - November 21st, 2018 - High Current Beam Test (MCC initiated)
- DAQ Testing - November 27th, 2018 - Testing injector timing
- DAQ Testing - November 28th, 2018 - Analyzing 27th's injector data
- DAQ Testing - December 2nd, 2018 - Follow-up injector timing tests
- DAQ Testing - December 3rd, 2018 - ET deadtime tests
- DAQ Testing - December 5th, 2018 - ET deadtime tests
- DAQ Testing - December 17th, 2018 - Conclusive ET deadtime tests
- DAQ Testing - December 19th, 2018 - Injector Banked CRL timing tests, BMW recommissioning in counting house
- DAQ Testing - December 21st, 2018 - Verify fiber optic cables for TS control are correct, SIS3801 in RHRS replace and test
- DAQ Testing - January 15th, 2019 - Notes from January up to 15th, crate sync tests and scaler updates
- DAQ Testing - January 18th, 2019 - Updating Japan to have the full detector map, and battery pedestal studies
- DAQ Testing - January 22nd, 2019 - Updating CH synch test to use JAPAN and vetoed logic modules
- DAQ Testing - January 23rd, 2019 - BMW testing FLEXIO and testing Online JAPAN ET connection
- DAQ Testing - February 4th, 2019 - DAQ exercising and SAM noise floor testing, Cavity BCMs update
- DAQ Testing - February 5th, 2019 - Working on getting the DAQ ready for APEX running
- DAQ Testing - February 6th, 2019 - Continuing
- DAQ Testing - February 7th, 2019 - Initialize TEDf 1546 test stand, getting helboard and HAPTB work started
- TEDf-VQWK-Testing - TEDf test stand summary page for module testing
- DAQ Testing - February 12th, 2019 - Helicity Control Board curiosities - new firmware is imperfect
- DAQ Testing - February 13th, 2019 - Helboard ctd. ADC testing
- DAQ Testing - March 22nd, 2019 - Online Japan Speed Limit
- DAQ Testing - April 4th, 2019 - Documenting Parity DAQ from APEX running
- DAQ Testing - April 29th, 2019 - Putting DAQ together for Summer running
- DAQ Testing - April 30th, 2019 - Getting batteries in place and new prminput maps
- DAQ Testing - May 1st, 2019 - Getting scripts ready and planning timing change
- DAQ Testing - May 2nd, 2019 - Stockpile spares and add Hall C bcms
- DAQ Testing - May 4th, 2019 - Spare STR 7200, INJ HAPTB
- DAQ Testing - May 8th, 2019 - Planning detector noise/pickup studies for following weeks
- DAQ Testing - May 23rd, 2019 - Testing new timing scheme and optimizing ADC integration placement
- DAQ Testing - June 3rd, 2019
- DAQ Testing - June 18th, 2019 - finalizing DAQ timing for 4 proposed modes
- DAQ Testing - June 28th, 2019 - Raster calibration
- DAQ Testing - June 30th, 2019 - running the parity DAQ with Lead to see Main detectors pickup the helicity flip
- DAQ Testing - July 14th, 2019 - DAQ TS issues, skipping events and eventual HRS DAQ adding helicity and TS replacement
- DAQ Testing - July 29th, 2019 - Testing with tune beam - DAQ bandwidth
- DAQ Testing - August 7th, 2019 - 240 Hz update, fixing /tmp/ overflow, and raster synch update for 240 Hz (primary goal is to get raster to work properly)