== WORK IN PROGRESS==
+
== Schedule ==
#Please don't worry if there is a needless test on here, or an important one missing, or bad prioritization.
+
* This is just a proposal, not settled.
# Lets fix it
+
<h3> Saturday </h3>
 +
*Swing: Pedestal Scan, PITA
 +
<h3> Sunday </h3>
 +
* Owl: Production
 +
* Day: Optics
 +
* Swing: Optics
 +
<h3> Monday </h3>
 +
* Owl: Final Q2 measurement.  Inelastic Scan. (If time, Poletip study?)
 +
* Day: Beam Studies
 +
* Swing: Beam Studies, Production (with Blind Quartz for check)
 +
<h3> Tuesday </h3>
 +
* Owl: Production
 +
* Day: Moller measurement. Sign check.
 +
* Swing: Production
 +
<h3> Wednesday </h3>
 +
*Owl: Production
 +
*Day: Raster and Target study
 +
*Swing: Production
 +
<h3> Thursday </h3>
 +
*Owl: Production
 +
*Day: '''DONE'''
  
 
== Optics and Q2 ==
 
== Optics and Q2 ==

Revision as of 12:52, 12 September 2020


CREX Main << August 2020 CREX Run Plan


Schedule

  • This is just a proposal, not settled.

Saturday

  • Swing: Pedestal Scan, PITA

Sunday

  • Owl: Production
  • Day: Optics
  • Swing: Optics

Monday

  • Owl: Final Q2 measurement. Inelastic Scan. (If time, Poletip study?)
  • Day: Beam Studies
  • Swing: Beam Studies, Production (with Blind Quartz for check)

Tuesday

  • Owl: Production
  • Day: Moller measurement. Sign check.
  • Swing: Production

Wednesday

  • Owl: Production
  • Day: Raster and Target study
  • Swing: Production

Thursday

  • Owl: Production
  • Day: DONE

Optics and Q2

  1. Energy Measurement (Doug) (non-invasive)
    • I think this is complete. I need to check with Doug.
  2. Q2 measurement
    • Repeat of Q2 measurement, with improved pedestal noise control.
    • Detector counting mode.
    • S0 trigger
    • production raster and beam position
  3. Optics Data

Backgrounds

  1. Blinded Quartz
    • Longish access to setup and back out, but short data taking period (production conditions).
    • Reconfigure AT detectors to use blinding cap, attach to US PMTs.
    • This will be done during the long beam studies break on Monday
    • Integrating measurement for asymmetry measurement
    • Counting mode measurement for rate?
    • Can we make a plan for yield measurement? Maybe use absolute table top gain measurements?
  2. Inelastic spectrum scan (~1 shift)
    • Needs a detailed run plan
    • Counting mode. Current 0.5uA or so? Turn quartz HV off.
    • Measure dp spectrum form dp=nominal to dp=-25%, in 5% steps.
    • should scale all spectrometer magnets (including septum)
    • Once the elastic peak is out of the focal plane, it may be possible turn on the S3 and S0 scintillator. This should be done when possible, and the T1/T2/T3 trigger rate recorded for each run.
  3. Pole tip re-scattering
    • Requires investigation or planning - do we have an idea here?
    • Q2 or septum mis-tune, to increase interception on pole tip and improve poletip rescattering estimate

Detectors

  1. Linearity Studies (PITA + current scans)
    • These are ongoing - should continue regularly. ~ 1 hour every 3 days.
    • Current scans for detector and BCM pedestals
  2. Linearity LED tests
    • This will be studied post run, during SAD
    • detector crew were left off the SAD access list - Kent needs to get this fixed.

Other

  1. Sign check
    • perform at next Moller polarimeter measurement
    • run Moller, Compton, and parity DAQ for quick PITA scan
  2. Target/Raster study


Moller polarimetry

  1. One more measurement

Compton polarimetry

  1. Flip DOCP???
  2. No-target runs
  3. Laser polarization optimization
  4. Laser polarization flip
  5. linearity studies