Difference between revisions of "RunPlanDaily"
Rich Holmes (talk | contribs) |
Rich Holmes (talk | contribs) |
||
Line 25: | Line 25: | ||
Quartz detectors checkout<br /> | Quartz detectors checkout<br /> | ||
GEM checkout<br /> | GEM checkout<br /> | ||
+ | Lumi checkout<br /> | ||
---- | ---- | ||
All at 1-2 µA. | All at 1-2 µA. | ||
Line 35: | Line 36: | ||
McNulty, Decowski, Wexler<br /> | McNulty, Decowski, Wexler<br /> | ||
Hansen, Camsonne, Liyanage<br /> | Hansen, Camsonne, Liyanage<br /> | ||
+ | Silwal, Mercado, D. Wang | ||
---- | ---- | ||
<br /> | <br /> | ||
Line 48: | Line 50: | ||
Quartz detectors checkout<br /> | Quartz detectors checkout<br /> | ||
GEM checkout<br /> | GEM checkout<br /> | ||
+ | Lumi checkout<br /> | ||
---- | ---- | ||
All at <~ 100 nA. </td> | All at <~ 100 nA. </td> | ||
Line 55: | Line 58: | ||
McNulty, Decowski, Wexler<br /> | McNulty, Decowski, Wexler<br /> | ||
Hansen, Camsonne, Liyanage<br /> | Hansen, Camsonne, Liyanage<br /> | ||
+ | Silwal, Mercado, D. Wang | ||
---- | ---- | ||
<br /></td><td>not done</td> </tr> | <br /></td><td>not done</td> </tr> | ||
</table> | </table> |
Revision as of 21:09, 19 March 2010
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Last update: Mar 19, 2010.
Date (2010) | Shift | ---------- Activity ---------- | -- Responsible -- | --- Status --- |
---|---|---|---|---|
03/19 | day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. |
Techs | in progress |
03/19 | swing | Beam restore | B-team | not done |
03/20 | owl | Septum checkout
also: All at 1-2 µA. |
Michaels, LeRose
| not done |
03/20 | day | Møller, Compton install Remove sieve |
Techs | not done |
03/20 | swing | Low current cavity monitors setup
Spectrometer checkout All at <~ 100 nA. |
Musson | not done |