Difference between revisions of "RunPlanDaily"

From PREX Wiki
Jump to navigationJump to search
(→‎Daily Run Plan: 3/21 owl, day)
Line 68: Line 68:
 
* Remove sieves (assuming low current cavities working)
 
* Remove sieves (assuming low current cavities working)
 
* <font color="red">Spectrometer checkout:</font>
 
* <font color="red">Spectrometer checkout:</font>
** Quartz detectors checkout (McNulty)
+
** Quartz detectors checkout (McNulty, Wexler)
 
** Lumi checkout (Mercado) (2 µA on Ta)
 
** Lumi checkout (Mercado) (2 µA on Ta)
 
** GEM checkout (Camsonne?)
 
** GEM checkout (Camsonne?)

Revision as of 21:39, 20 March 2010

Daily Run Plan

Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.


Daily Run Plan for PREX   (latest at bottom)
Date (2010) Shift ---------- Activity (Responsible) ---------- --- Status ---
03/19 day pump down; Møller, Compton, septum install; Q2 repair

Insert sieve. (Techs)

03/19 swing Beam restore (B-team) done
03/20 owl
  • Septum checkout (Michaels: Page when beam imminent & spectrometer ready)

also:

  • Initial look at low current cavity monitors (Zafar: Page when beam imminent & spectrometer ready)
  • Target alignment (Michaels)
  • VDC checkout (Michaels)
  • Quartz detectors checkout (McNulty, Wexler -- page when VDC tracks seen)
  • GEM checkout (Camsonne -- page when VDC tracks seen, if left dipole is operating)

All at 1-2 µA.
Scattered energy ~ beam energy = 1.063 GeV.
Quad settings:

  • Right arm:
    • Q1: dI/dP= 411.2474 Amps/GeV/c
    • Q2: dI/dP= 436.2014 Amps/GeV/c
    • Q3: dI/dP= 433.3897 Amps/GeV/c
  • Left Arm:
    • Q1: dI/dP= 419.8772 Amps/GeV/c
    • Q2: dI/dP= 435.6273 Amps/GeV/c
    • Q3: dI/dP= 434.9682 Amps/GeV/c

"Usual" polarity

done
03/20 day Beam off & hall open 9:00 am

Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs)

done
03/20 swing
  • Close up hall
  • Benesch tuning (1/2 - 2 hours)
  • Verify quad polarities (Camsonne)
  • Cavity monitors basic function test (Zafar)
  • Low current cavity monitors setup (Musson, Zafar) (2 hours)
in progress
3/21 owl
  • Access for GEM installation (Camsonne)
  • Remove sieves (assuming low current cavities working)
  • Spectrometer checkout:
    • Quartz detectors checkout (McNulty, Wexler)
    • Lumi checkout (Mercado) (2 µA on Ta)
    • GEM checkout (Camsonne?)

At <~ 100 nA up to few µA.

not done
3/21 day
  • Put in water cell
  • Pointing measurement
  • A_T hole?

Page Jack Segal if long access.

not done