Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchRich Holmes (talk | contribs) (→Daily Run Plan: tentative Mon-Tue) |
Rich Holmes (talk | contribs) (→Daily Run Plan: 3/21 day/swing revision) |
||
Line 59: | Line 59: | ||
* Verify quad polarities (Camsonne) | * Verify quad polarities (Camsonne) | ||
* Cavity monitors basic function test (Zafar) | * Cavity monitors basic function test (Zafar) | ||
− | * <font color="red">Low current cavity monitors setup (Musson, Zafar)</font> | + | * <font color="red">Low current cavity monitors setup (Musson, Zafar)</font> |
− | | | + | | most done but need access to finish |
|- | |- | ||
| 3/21 | | 3/21 | ||
| owl | | owl | ||
| | | | ||
+ | * <font color="red">Low current cavity monitors setup (Musson, Zafar)</font> | ||
* Access for GEM installation (Camsonne) | * Access for GEM installation (Camsonne) | ||
− | + | | most done but need access to finish | |
+ | |- | ||
+ | | 3/21 | ||
+ | | day | ||
+ | | | ||
* <font color="red">Spectrometer checkout:</font> | * <font color="red">Spectrometer checkout:</font> | ||
** Quartz detectors checkout (McNulty, Wexler) | ** Quartz detectors checkout (McNulty, Wexler) | ||
** Lumi checkout (Mercado) (2 µA on Ta) | ** Lumi checkout (Mercado) (2 µA on Ta) | ||
** GEM checkout (Camsonne?) | ** GEM checkout (Camsonne?) | ||
− | + | * A line tuning (Benesch) | |
− | + | * Raster checkout | |
+ | * Access: | ||
+ | ** Low current cavities | ||
+ | ** Target position | ||
+ | ** Quartz | ||
+ | * <font color="red">Low current cavity monitors setup (Michaels, Zafar)</font> | ||
+ | * Remove sieves (assuming low current cavities working) | ||
| not done | | not done | ||
|- | |- | ||
| 3/21 | | 3/21 | ||
− | | | + | | swing |
| | | | ||
* <font color="red">Pointing measurement</font> | * <font color="red">Pointing measurement</font> | ||
* A_T hole? | * A_T hole? | ||
− | |||
− | |||
| not done | | not done | ||
− | |||
− | |||
− | |||
− | |||
− | |||
|- | |- | ||
| 3/22 | | 3/22 |
Revision as of 11:43, 21 March 2010
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Date (2010) | Shift | ---------- Activity (Responsible) ---------- | --- Status --- |
---|---|---|---|
03/19 | day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. (Techs) |
|
03/19 | swing | Beam restore (B-team) | done |
03/20 | owl |
also:
All at 1-2 µA.
"Usual" polarity |
done |
03/20 | day | Beam off & hall open 9:00 am Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs) |
done |
03/20 | swing |
|
most done but need access to finish |
3/21 | owl |
|
most done but need access to finish |
3/21 | day |
|
not done |
3/21 | swing |
|
not done |
3/22 | owl | ||
3/22 | day | RQ2 repair | |
3/22 | swing | Pointing measurement | |
3/23 | owl | ||
3/23 | day | Beam studies Remove water target |