Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchLine 130: | Line 130: | ||
* Reconfigure Moller cryo. | * Reconfigure Moller cryo. | ||
* '''Beam studies''' ~ 2pm, study of helicity correlated position differences for spin flipper states. (Dalton, Rupesh, Reza) | * '''Beam studies''' ~ 2pm, study of helicity correlated position differences for spin flipper states. (Dalton, Rupesh, Reza) | ||
− | | | + | |- |
− | |||
− | |||
| 3/23 | | 3/23 | ||
| Swing | | Swing | ||
Line 146: | Line 144: | ||
| Day | | Day | ||
| | | | ||
− | Commission lead target | + | * Commission lead target, 50 uA (Bob) |
+ | * Lumis and oversampling tests (KK, Luis, Paul) | ||
+ | | | ||
+ | |- | ||
+ | | 3/24 | ||
+ | | Swing | ||
+ | | | ||
+ | * Lead target, Lumis, oversampling (cont.) | ||
+ | | | ||
+ | |- | ||
+ | | 3/25 | ||
+ | | Owl | ||
+ | | | ||
+ | * Parity Quality commissioning (Kent, Rupesh, Luis, Dustin) | ||
+ | * Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng) | ||
+ | | | ||
+ | |- | ||
+ | | 3/25 | ||
+ | | Day | ||
+ | | | ||
+ | * High Luminosity Detector Commissioning | ||
+ | | | ||
+ | |- | ||
+ | | 3/25 | ||
+ | | Swing | ||
+ | | | ||
+ | * Establish Q2 measurement sequence (Dustin, Nilanga) | ||
+ | * ARC energy measurement (Arun Saha) | ||
+ | | | ||
+ | |- | ||
+ | | 3/26 | ||
+ | | Owl | ||
+ | | | ||
+ | *Moller Checkout | ||
+ | | | ||
+ | |- | ||
+ | | 3/26 | ||
+ | | Day | ||
+ | | | ||
+ | *Moller Checkout | ||
+ | | | ||
+ | |- | ||
+ | | 3/26 | ||
+ | | Swing | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | 3/27 | ||
+ | | Owl | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | 3/27 | ||
+ | | Day | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | 3/27 | ||
+ | | Swing | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | 3/28 | ||
+ | | Owl | ||
+ | | | ||
+ | | | ||
+ | |- | ||
+ | | 3/28 | ||
+ | | Day | ||
+ | | | ||
| | | | ||
− | |||
|} | |} |
Revision as of 15:05, 23 March 2010
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Date (2010) | Shift | ---------- Activity (Responsible) ---------- | --- Status --- |
---|---|---|---|
03/19 | Day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. (Techs) |
|
03/19 | Swing | Beam restore (B-team) | done |
03/20 | Owl |
also:
All at 1-2 µA.
"Usual" polarity |
done |
03/20 | Day | Beam off & hall open 9:00 am Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs) |
done |
03/20 | Swing |
|
most done but need access to finish |
3/21 | Owl |
|
most done but need access to finish |
3/21 | Day |
|
in progress |
3/21 | Swing |
|
not done |
3/22 | Owl |
|
|
3/22 | Day |
|
|
3/22 | Swing |
|
|
3/23 | Owl |
|
|
3/23 | Day |
| |
3/23 | Swing | ||
3/24 | Owl | ||
3/24 | Day |
|
|
3/24 | Swing |
|
|
3/25 | Owl |
|
|
3/25 | Day |
|
|
3/25 | Swing |
|
|
3/26 | Owl |
|
|
3/26 | Day |
|
|
3/26 | Swing | ||
3/27 | Owl | ||
3/27 | Day | ||
3/27 | Swing | ||
3/28 | Owl | ||
3/28 | Day |
|