Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchLine 203: | Line 203: | ||
| 3/27 | | 3/27 | ||
| Day | | Day | ||
+ | | | ||
*Electronic Commissioning (KK, Luis, Paul et al) | *Electronic Commissioning (KK, Luis, Paul et al) | ||
| | | | ||
Line 208: | Line 209: | ||
| 3/27 | | 3/27 | ||
| Swing | | Swing | ||
+ | | | ||
*Establishing Parity Measurements, IA feedback, beam modulation (Kent, Rupesh) | *Establishing Parity Measurements, IA feedback, beam modulation (Kent, Rupesh) | ||
| | | | ||
Line 213: | Line 215: | ||
| 3/28 | | 3/28 | ||
| Owl | | Owl | ||
+ | | | ||
*Initial Q<sup>2</sup> measauremetnts on thick Pb (Bob) | *Initial Q<sup>2</sup> measauremetnts on thick Pb (Bob) | ||
| | | | ||
Line 218: | Line 221: | ||
| 3/28 | | 3/28 | ||
| Day | | Day | ||
+ | | | ||
*High Luminosity Detector Commissioning (Paul, Kent, KK, Luis) | *High Luminosity Detector Commissioning (Paul, Kent, KK, Luis) | ||
| | | | ||
Line 223: | Line 227: | ||
| 3/28 | | 3/28 | ||
| Swing | | Swing | ||
+ | | | ||
*Continue High Luminosity Commissioning | *Continue High Luminosity Commissioning | ||
| | | | ||
Line 228: | Line 233: | ||
| 3/29 | | 3/29 | ||
| Owl | | Owl | ||
− | *Mini-production run | + | | |
+ | *Mini-production run (shift crew) | ||
+ | *Stop beam at 06:30. | ||
| | | | ||
|- | |- | ||
| 3/29 | | 3/29 | ||
| Day | | Day | ||
+ | | | ||
*Open Hall A to Setup Moller and Compton | *Open Hall A to Setup Moller and Compton | ||
| | | | ||
Line 238: | Line 246: | ||
| 3/29 | | 3/29 | ||
| Swing | | Swing | ||
− | *First Moller Commissioning | + | | |
+ | *First Moller Commissioning (Sasha) | ||
| | | | ||
|- | |- |
Revision as of 21:51, 26 March 2010
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Date (2010) | Shift | ---------- Activity (Responsible) ---------- | --- Status --- | |
---|---|---|---|---|
03/19 | Day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. (Techs) |
||
03/19 | Swing | Beam restore (B-team) | done | |
03/20 | Owl |
also:
|
done
All at 1-2 µA.
"Usual" polarity |
done |
03/20 | Day | Beam off & hall open 9:00 am Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs) |
done | |
03/20 | Swing |
|
done | |
3/21 | Owl |
|
done but GEMs not ready | |
3/21 | Day |
|
done | |
3/21 | Swing |
|
done | |
3/22 | Owl |
|
done | |
3/22 | Day |
|
done | |
3/22 | Swing |
|
done | |
3/23 | Owl |
|
||
3/23 | Day |
| ||
3/23 | Swing |
|
done | |
3/24 | Owl |
|
done | |
3/24 | Day |
|
done | |
3/24 | Swing |
|
done | |
3/25 | Owl |
|
in progress | |
3/25 | Day |
|
||
3/25 | Swing |
|
||
3/26 | Owl |
|
||
3/26 | Day |
|
postponed | |
3/26 | Swing |
|
||
3/27 | Owl |
|
||
3/27 | Day |
|
||
3/27 | Swing |
|
||
3/28 | Owl |
|
||
3/28 | Day |
|
||
3/28 | Swing |
|
||
3/29 | Owl |
|
||
3/29 | Day |
|
||
3/29 | Swing |
|
||
3/30 | Owl | |||
3/30 | Day |
|