Jump to navigationJump to searchLine 167: | Line 167: | ||
| | | | ||
* Access to fix left dipole | * Access to fix left dipole | ||
− | | | + | |done |
|- | |- | ||
| 3/25 | | 3/25 | ||
Line 174: | Line 174: | ||
* Parity Quality commissioning (Kent, Rupesh, Luis, Dustin) | * Parity Quality commissioning (Kent, Rupesh, Luis, Dustin) | ||
* Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng) | * Beam monitor calibrations (Diancheng Wang, Xiaoyan Deng) | ||
− | | | + | |postponed |
|- | |- | ||
| 3/26 | | 3/26 | ||
Line 253: | Line 253: | ||
| 3/30 | | 3/30 | ||
| Owl | | Owl | ||
+ | | | ||
*Parity-Quality Beam Setup (Kent, Rupesh, Mark) | *Parity-Quality Beam Setup (Kent, Rupesh, Mark) | ||
| | | | ||
Line 258: | Line 259: | ||
| 3/30 | | 3/30 | ||
| Day | | Day | ||
+ | | | ||
*Possible work in Hall ... TBD | *Possible work in Hall ... TBD | ||
| | | |
Revision as of 22:02, 26 March 2010
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Date (2010) | Shift | ---------- Activity (Responsible) ---------- | --- Status --- | |
---|---|---|---|---|
03/19 | Day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. (Techs) |
||
03/19 | Swing | Beam restore (B-team) | done | |
03/20 | Owl |
also:
|
done
All at 1-2 µA.
"Usual" polarity |
done |
03/20 | Day | Beam off & hall open 9:00 am Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs) |
done | |
03/20 | Swing |
|
done | |
3/21 | Owl |
|
done but GEMs not ready | |
3/21 | Day |
|
done | |
3/21 | Swing |
|
done | |
3/22 | Owl |
|
done | |
3/22 | Day |
|
done | |
3/22 | Swing |
|
done | |
3/23 | Owl |
|
||
3/23 | Day |
| ||
3/23 | Swing |
|
done | |
3/24 | Owl |
|
done | |
3/24 | Day |
|
done | |
3/24 | Swing |
|
done | |
3/25 | Owl |
|
in progress | |
3/25 | Day |
|
done | |
3/25 | Swing |
|
postponed | |
3/26 | Owl |
|
||
3/26 | Day |
|
postponed | |
3/26 | Swing |
|
||
3/27 | Owl |
|
||
3/27 | Day |
|
||
3/27 | Swing |
|
||
3/28 | Owl |
|
||
3/28 | Day |
|
||
3/28 | Swing |
|
||
3/29 | Owl |
|
||
3/29 | Day |
|
||
3/29 | Swing |
|
||
3/30 | Owl |
|
||
3/30 | Day |
|
|