Difference between revisions of "RunPlanDaily"

From PREX Wiki
Jump to navigationJump to search
Line 134: Line 134:
 
|-
 
|-
 
| Day  
 
| Day  
| Spin dance.  
+
| Send beam through Compton chicane.  
 
|  
 
|  
 
|-
 
|-

Revision as of 16:22, 25 June 2019

In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.

PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Monday, June 17 Owl
Day Last day for planned collaboration work in Hall. Expecting 2A alignment
Swing Vacuum connections between US pipe and target and between target and collimator box.
Tuesday, June 18 Owl
Day Pump down the entire pivot to dump region; Expecting 2B alignment
Swing Target software checks
Wednesday, June 19 Owl
Day Hall Closed. Final Checklist. Possible first beam in Hall A
Swing Continue beam in Hall A for tuning. Start low beam checkout.
Thursday, June 20 Owl Continue low beam current checkout. Completed Collimator search.
Day Tuning
Swing Tune up and Low current commissioning.
Friday, June 21 Owl Low current commissioning. Started optics Commissioned 45deg and 90deg targets. Calibrated ion chambers. Bullseye scan.
Day High current + Compton rate tuning.
Swing High current calibration after tuning (Caryn). Low current commissioning. Restart Optics (Seamus, Sanghwa, Ryan) Basic run quality plot macro needed (Sanghwa).
Saturday, June 22 Owl Opportunistic: Beam Modulation (Paul K, Vectoria) ESR 15K helium issue, scattering chamber vacuum degration investigation
Day Optics.
Swing Low current cavity (Ye, Cip). Minimum chase.
Sunday, June 23 Owl Inner edge search (Bob, Chandan, Kent). Q2 measurement with Pb target (Bob?). Opportunistic: Beam Modulation (Paul K, Vectoria) Inner edge search DONE.
Day Minimize width.
Swing Minimize width. Minimum chase.
Monday, June 24 Owl Quartz align; quartz rate. (Dustin)
Day Optics verification. ESR 15K helium repair is ongoing.
Swing No beam.
Tuesday, June 25 Owl No beam. shift cancelled.
Day Target cooling down. shift cancelled
Swing Low current cavity lock test. SAM test. optics
Wednesday, June 26 Owl optics
Day Send beam through Compton chicane.
Swing optics.
Thursday, June 27 Owl Q^2 on thin lead target (Bob or Kent).
Day Compton commissioning. Beam instrumentation calculation (Caryn) Production condition test (Caryn)
Swing Width Studies (KK)
Friday, June 28 Owl
Day
Swing

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting