! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
 
! style="width:10%"|  Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status
|-
 
| rowspan="3" | Monday, June 17
 
| Owl
 
|
 
|
 
|-
 
| Day
 
| Last day for planned collaboration work in Hall.
 
| Expecting 2A alignment
 
|-
 
| Swing 
 
| Vacuum connections between US pipe and target and between target and collimator box.
 
|
 
|-
 
| rowspan="3" | Tuesday, June 18
 
| Owl
 
|
 
|
 
|-
 
| Day
 
|
 
| Pump down the entire pivot to dump region; Expecting 2B alignment
 
|-
 
| Swing
 
|
 
| Target software checks
 
|-
 
| rowspan="3" | Wednesday, June 19
 
| Owl
 
|
 
|
 
|-
 
| Day ||
 
|  Hall Closed. Final Checklist. Possible first beam in Hall A
 
|-
 
| Swing
 
| Continue beam in Hall A for tuning. Start low beam checkout.
 
|
 
|-
 
| rowspan="3" | Thursday, June 20
 
| Owl
 
| Continue low beam current checkout.
 
| Completed Collimator search.
 
|-
 
| Day
 
| Tuning
 
|
 
|-
 
| Swing
 
| Tune up and Low current commissioning.
 
|
 
|-
 
| rowspan="3" | Friday, June 21
 
| Owl
 
| Low current commissioning. Started optics
 
| Commissioned 45deg and 90deg targets. Calibrated ion chambers.  Bullseye scan.
 
|-
 
| Day
 
| High current + Compton rate tuning.
 
|-
 
| Swing
 
|High current calibration after tuning (Caryn). Low current commissioning.  Restart Optics (Seamus, Sanghwa, Ryan)
 
| Basic run quality plot macro needed (Sanghwa).
 
|-
 
| rowspan="3" | Saturday, June 22
 
| Owl
 
| Opportunistic: Beam Modulation (Paul K, Vectoria)
 
| ESR 15K helium issue, scattering chamber vacuum degration investigation
 
|-
 
| Day
 
| Optics.
 
|
 
|-
 
| Swing
 
| Low current cavity (Ye, Cip). Minimum chase.
 
|
 
|-
 
| rowspan="3" | Sunday, June 23
 
| Owl
 
| Inner edge search (Bob, Chandan, Kent). Q2 measurement with Pb target (Bob?). Opportunistic: Beam Modulation (Paul K, Vectoria)
 
| Inner edge search DONE.
 
|-
 
| Day
 
| Minimize width.
 
|
 
|-
 
| Swing
 
| Minimize width. Minimum chase.
 
|
 
|-
 
| rowspan="3" | Monday, June 24
 
| Owl
 
| Quartz align; quartz rate. (Dustin)
 
|
 
|-
 
| Day
 
| Optics verification.
 
| ESR 15K helium repair is ongoing.
 
|-
 
| Swing
 
|
 
| No beam. 
 
 
|-
 
|-
 
| rowspan="3" | Tuesday, June 25
 
| rowspan="3" | Tuesday, June 25

Revision as of 14:55, 26 June 2019

In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.

PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Tuesday, June 25 Owl No beam. shift cancelled.
Day Target cooling down. shift cancelled
Swing Optics. Vacuum issue. No beam for the whole shift.
Wednesday, June 26 Owl Optics.
Day Optics. Send beam through Compton chicane. Optics complete. Vacuum valve VBV1P03 (compton table) can't be opened.
Swing Low current cavity lock test. Optics. Q^2 measurement (Bob or Kent). Opportunistic: SAM test.
Thursday, June 27 Owl Detector alignment. Detector rate.
Day Send beam through Compton chicane. Compton commissioning. Beam instrumentation calculation (Caryn)
Swing Production condition test. Width Studies (KK)
Friday, June 28 Owl
Day
Swing
Saturday, June 29 Owl
Day
Swing
Sunday, June 30 Owl
Day Moller commissioning.
Swing

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting