− | | | + | | 70 microAmp production, FFB, Detector and SAM calibration |
| | | | ||
|- | |- |
Revision as of 09:31, 17 July 2019
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Sunday, July 14 | Owl | Production+ analysis. FFB (30 min), BMW (30 min), Aq | FFB tried, but didn't work. |
Day | Production+ analysis | ||
Swing | Production+ analysis | ||
Monday, July 15 | Owl | Production+ analysis. | Except ~3 hour down time, we took good data |
Day | FFB commissioning until 10AM. Take run with FFB (if ready) or w/o FFB (if not ready) until MOLLER experts walk in for MOLLER commissioning. | MOLLER polarimeter commissioning is going on | |
Swing | MOLLER commissioning | ||
Tuesday, July 16 | Owl | MOLLER Polarimeter and FFB commissioning | |
Day | production after pass change | ||
Swing | change IHWP ('out'), BPM and BCM calibration (Caryn) | Done | |
Wednesday, July 17 | Owl | Production with 50uA with Aq, BMW and Energy-mode:'RF-off' | |
Day | 70 microAmp production, FFB, Detector and SAM calibration | ||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting