Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchLine 109: | Line 109: | ||
| Production running at 70uA | | Production running at 70uA | ||
| | | | ||
− | |- | + | |- |
| rowspan="3" | Sunday, August 18 | | rowspan="3" | Sunday, August 18 | ||
| Owl | | Owl | ||
Line 118: | Line 118: | ||
| Moller measurement | | Moller measurement | ||
| | | | ||
− | |- | + | |- |
| Swing | | Swing | ||
| Production running at 70uA | | Production running at 70uA | ||
Line 125: | Line 125: | ||
# 70 uA beam restored to hall | # 70 uA beam restored to hall | ||
# Production running | # Production running | ||
− | |- | + | |-style="background: #FCF3CF; |
| rowspan="3" | Monday, August 19 | | rowspan="3" | Monday, August 19 | ||
| Owl | | Owl | ||
| Production running at 70uA | | Production running at 70uA | ||
| | | | ||
− | |- | + | |-style="background: #FCF3CF; |
| Day | | Day | ||
| Production running at 70uA | | Production running at 70uA | ||
| | | | ||
− | |- | + | |-style="background: #FCF3CF; |
| Swing | | Swing | ||
| Production running at 70uA | | Production running at 70uA |
Revision as of 23:27, 18 August 2019
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, August 12 | Owl | Production running at 70uA with | |
Day |
|
||
Swing | Production running at 70uA | ||
Tuesday, August 13 | Owl | Production running at 70uA | |
Day |
| ||
Swing | Transverse Polarized Measurement | ||
Wednesday, August 14 | Owl | Transverse Polarized Measurement | |
Day |
|
| |
Swing
|
Production running at 70uA |
| |
Thursday, August 15 | Owl | Production running at 70uA | |
Day | Production running at 70uA | ||
Swing | Production running at 70uA |
| |
Friday, August 16 | Owl | Production running at 70uA | Beam off at 7 AM to cool down the hall prior to Compton work |
Day |
|
| |
Swing | Production running at 70uA | No beam due to CHL and Hall B restore | |
Saturday, August 17 | Owl | Production running at 70uA | No beam due to CHL and Hall B restore |
Day | Production running at 70uA |
| |
Swing | Production running at 70uA | ||
Sunday, August 18 | Owl | Production running at 70uA | |
Day | Moller measurement | ||
Swing | Production running at 70uA |
| |
Monday, August 19 | Owl | Production running at 70uA | |
Day | Production running at 70uA | ||
Swing | Production running at 70uA | ||
Tuesday, August 20 | Owl | Production running at 70uA | |
Day | |||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting