Difference between revisions of "RunPlanDaily CREX"

From PREX Wiki
Jump to navigationJump to search
Line 48: Line 48:
 
|-
 
|-
 
| Swing
 
| Swing
| lock up; continue low current commissioning
+
| lock up; reverse septum polarity; raster size and hole locations
| Target position alignment checks; authorize 150 uA (before 5pm)?
+
| Left arm NMR probe lock not working; couldn't put any beam on Ca-40 (dump FSDs)
 
|-
 
|-
 
| rowspan="3" | Saturday, December 7
 
| rowspan="3" | Saturday, December 7
 
| Owl
 
| Owl
| start spectrometer commissioning
+
| Tried ion-chamber calibration, but failed; started spec commissioning
| https://prex.jlab.org/wiki/index.php/CREXRunPlan#Spectrometer_Commissioning
+
| First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped
 
|-
 
|-
 
| Day
 
| Day
| commissioning/ Q2 measurement and Spectrometer rescattering
+
| Jay setup our transport optics,...
| https://prex.jlab.org/wiki/index.php/RescatteringPlan
+
| Found out reason for raster optics issues: Moller quads not set correctly
 
|-
 
|-
 
| Swing
 
| Swing

Revision as of 16:15, 7 December 2019



CREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Comments/Status
Wednesday, December 4 Owl No shift
Day Magnet work...
Swing Magnet work...until Jack ready to leave 4-8pm. Then 5pass tuning into A.
Thursday, December 5 Owl Then 5pass tuning into A.
Day RF stress test to A/RF fixing Burned up 3 raster power supplies (ended test at 4:15pm!)
Swing Go to 1 pass; Septum problem (only up to 400 A); collimator centering; polarity check Set HRS tune P for this septum setting for polarity check
Friday, December 6 Owl spectrometer setup did not allow target alignment checks Beam gone at 3:40am due to Network issue
Day Hall surveyed/controlled access all day; remove diffusor at end? Septum fix; compton work; network issues run down; raster sync investigated
Swing lock up; reverse septum polarity; raster size and hole locations Left arm NMR probe lock not working; couldn't put any beam on Ca-40 (dump FSDs)
Saturday, December 7 Owl Tried ion-chamber calibration, but failed; started spec commissioning First pass optics DB looks good; started septum setting and inner edge searches. Right dipole tripped
Day Jay setup our transport optics,... Found out reason for raster optics issues: Moller quads not set correctly
Swing commissioning
Sunday, December 8 Owl commissioning
Day commissioning
Swing commissioning
Monday, December 9 Owl commissioning
Day diffusor out (if not already); spin dance? Spin dance if Hall C ready
Swing commissioning/production
Tuesday, December 10 Owl commissioning/production
Day production
Swing production

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting