(Created page with ' == PREX Run Plan == '''Part I: List of Tasks''' Here is a list of tasks in approximate time order, with person(s) responsible, approximate amount of time required, and commen…')
 
Line 6: Line 6:
 
Here is a list of tasks in approximate time order, with person(s) responsible, approximate amount of time required, and comments about the conditions or needs.  The time will, in most cases, be broken up into manageable chunks.
 
Here is a list of tasks in approximate time order, with person(s) responsible, approximate amount of time required, and comments about the conditions or needs.  The time will, in most cases, be broken up into manageable chunks.
  
I. Basic Beam Setup -- Jay Benesch, Bteam
+
I. Basic Beam Setup -- Jay Benesch, Bteam <br>
 
II. Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal
 
II. Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal
 
III. Septum Commissioning -- Bob Michaels, John LeRose
 
III. Septum Commissioning -- Bob Michaels, John LeRose

Revision as of 13:35, 25 January 2010

PREX Run Plan

Part I: List of Tasks

Here is a list of tasks in approximate time order, with person(s) responsible, approximate amount of time required, and comments about the conditions or needs. The time will, in most cases, be broken up into manageable chunks.

I. Basic Beam Setup -- Jay Benesch, Bteam
II. Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal III. Septum Commissioning -- Bob Michaels, John LeRose --- a) Verify septum does not steer beam --- b) Thin target, low-current checks IV. Water Cell and Optics of HRS+Septum -- Nilanga Liyanage


Part II: Schedule