Difference between revisions of "RunPlan"
From PREX Wiki
Jump to navigationJump to searchLine 7: | Line 7: | ||
<UL> | <UL> | ||
− | <LI> Basic Beam Setup -- Jay Benesch, Bteam <br> | + | <LI> <font color="blue">Basic Beam Setup</font> -- <font color="green">12 hrs</font> Jay Benesch, Bteam <br> |
<LI> Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal <br> | <LI> Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal <br> | ||
<LI> Septum Commissioning -- Bob Michaels, John LeRose | <LI> Septum Commissioning -- Bob Michaels, John LeRose |
Revision as of 13:37, 25 January 2010
PREX Run Plan
Part I: List of Tasks
Here is a list of tasks in approximate time order, with person(s) responsible, approximate amount of time required, and comments about the conditions or needs. The time will, in most cases, be broken up into manageable chunks.
- Basic Beam Setup -- 12 hrs Jay Benesch, Bteam
- Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal
- Septum Commissioning -- Bob Michaels, John LeRose
- Verify septum does not steer beam
- Thin target, low-current checks
- Water Cell and Optics of HRS+Septum -- Nilanga Liyanage
Part II: Schedule