Revision as of 22:04, 19 March 2010

Daily Run Plan

Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.

Last update: Mar 19, 2010.


Daily Run Plan for PREX   (latest at bottom)
Date (2010) Shift ---------- Activity ------------ Responsible ----- Status ---
03/19 day pump down; Møller, Compton, septum install; Q2 repair
Insert sieve.
Techs
03/19 swing Beam restore B-team not done
03/20 owl Septum checkout

also:
Initial look at low current cavity monitors
Target alignment
VDC checkout
Quartz detectors checkout
GEM checkout


All at 1-2 µA.

Michaels, LeRose


Michaels, Zafar
Michaels
McNulty, Camsonne, Michaels
McNulty, Wexler
Camsonne



not done
03/20 day Quads repair; Compton install
Remove sieve
Techs not done
03/20 swing Low current cavity monitors setup

Spectrometer checkout
VDC checkout
Quartz detectors checkout
GEM checkout
Lumi checkout


All at <~ 100 nA.

Musson

McNulty, Camsonne, Michaels
McNulty, Decowski, Wexler
Hansen, Camsonne, Liyanage
Silwal, Mercado, D. Wang



not done