Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchLine 431: | Line 431: | ||
| Owl | | Owl | ||
| | | | ||
− | * Shift | + | * Shift cancelled |
| | | | ||
|- | |- | ||
Line 437: | Line 437: | ||
| Day | | Day | ||
| | | | ||
− | *Shift | + | *Shift cancelled |
− | * Investigate target vacuum problem | + | * Investigate target vacuum problem |
* Move quartz detectors (Dustin, Jack) | * Move quartz detectors (Dustin, Jack) | ||
− | | | + | |done. Leak found at O-ring connection between target chamber and collimator box |
|- | |- | ||
| Wednesday 7 April | | Wednesday 7 April | ||
| Swing | | Swing | ||
| | | | ||
− | *Shift | + | *Shift cancelled |
− | |||
− | |||
| | | | ||
|- | |- | ||
Line 453: | Line 451: | ||
| Owl | | Owl | ||
| | | | ||
− | *Shift | + | *Shift cancelled |
|- | |- | ||
| Thursday 8 April | | Thursday 8 April | ||
| Day | | Day | ||
| | | | ||
− | *Shift | + | *Shift cancelled |
| | | | ||
|- | |- | ||
Line 464: | Line 462: | ||
| Swing | | Swing | ||
| | | | ||
− | *Shift | + | *Shift cancelled |
| | | | ||
|- | |- | ||
Line 470: | Line 468: | ||
| Owl | | Owl | ||
| | | | ||
− | *Shift | + | *Shift cancelled |
| | | | ||
|- | |- | ||
Line 476: | Line 474: | ||
| Day | | Day | ||
| | | | ||
+ | * To be determined. | ||
* When ready: Install GEMs | * When ready: Install GEMs | ||
| | | | ||
Line 482: | Line 481: | ||
| Swing | | Swing | ||
| | | | ||
− | * | + | * When we resume: Align newly placed quartz detector |
| | | | ||
|- | |- | ||
Line 488: | Line 487: | ||
| Owl | | Owl | ||
| | | | ||
− | * Production | + | * Production (TBD) |
| | | | ||
|- | |- | ||
Line 494: | Line 493: | ||
| Day | | Day | ||
| | | | ||
− | * Production | + | * Production (TBD) |
+ | * Possible commissioning of Moller and Compton (TBD) | ||
| | | | ||
|- | |- | ||
Line 500: | Line 500: | ||
| Swing | | Swing | ||
| | | | ||
− | * Production | + | * Production (TBD) |
| | | | ||
|- | |- | ||
Line 506: | Line 506: | ||
| Owl | | Owl | ||
| | | | ||
− | * Production | + | * Production (TBD) |
| | | | ||
|- | |- | ||
Line 512: | Line 512: | ||
| Day | | Day | ||
| | | | ||
− | * Production | + | * Production (TBD) |
| | | | ||
|- | |- | ||
Line 518: | Line 518: | ||
| Swing | | Swing | ||
| | | | ||
− | * Production | + | * Production (TBD) |
| | | | ||
|- | |- | ||
Line 524: | Line 524: | ||
| Owl | | Owl | ||
| | | | ||
− | * Production | + | * Production (TBD) |
| | | | ||
|- | |- | ||
Line 530: | Line 530: | ||
| Day | | Day | ||
| | | | ||
− | * Moller | + | * Either: |
+ | * Moller Commissioning | ||
+ | * Or continue fixing the target vacuum chamber | ||
| | | | ||
|- | |- |
Revision as of 22:24, 7 April 2010
Daily Run Plan
Here are details of the daily run plan. See also the Global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Date (2010) | Shift | ---------- Activity (Responsible) ---------- | --- Status --- |
---|---|---|---|
03/19 | Day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. (Techs) |
done |
03/19 | Swing | Beam restore (B-team) | done |
03/20 | Owl |
also:
|
done
All at 1-2 µA.
"Usual" polarity |
03/20 | Day | Beam off & hall open 9:00 am Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs) |
done |
03/20 | Swing |
|
done |
3/21 | Owl |
|
done but GEMs not ready |
3/21 | Day |
|
done |
3/21 | Swing |
|
done |
3/22 | Owl |
|
done |
3/22 | Day |
|
done |
3/22 | Swing |
|
done |
3/23 | Owl |
|
|
3/23 | Day |
|
water cell removed, rest not finished |
3/23 | Swing |
|
done |
3/24 | Owl |
|
done |
3/24 | Day |
|
done |
3/24 | Swing |
|
done |
3/25 | Owl |
|
in progress |
3/25 | Day |
|
done |
3/25 | Swing |
|
postponed |
3/26 | Owl |
|
in progress |
3/26 | Day |
|
postponed |
3/26 | Swing |
|
partly done |
3/27 | Owl | no beam | |
3/27 | Day | no beam | |
3/27 | Swing |
|
done, high-current tests continue |
3/28 | Owl |
|
not finished |
3/28 | Day |
|
done |
3/28 | Swing |
|
done |
3/29 | Owl |
|
done |
3/29 | Day |
|
done |
3/29 | Swing |
|
done |
3/30 | Owl |
|
done |
3/30 | Day |
|
done, except linearity |
3/30 | Swing |
|
done |
3/31 | Owl |
|
done |
3/31 | Day |
|
|
3/31 | Swing |
|
Moller was done |
4/1 | Owl |
|
done |
4/1 | Day |
|
done, successful |
4/1 | Swing |
|
done |
Friday 2 April | Owl |
|
partly done, needs more work |
Friday 2 April | Day |
|
done |
Friday 2 April | Swing |
|
done, but not Q2 |
Saturday 3 April | Owl |
|
done |
Saturday 3 April | Day |
|
done, but not yet in prod. |
Saturday 3 April | Swing |
|
done |
Sunday 4 April | Owl |
|
done |
Sunday 4 April | Day |
|
done |
Sunday 4 April | Swing |
|
done |
Monday 5 April | Owl |
|
done |
Monday 5 April | Day |
|
done |
Monday 5 April | Swing |
|
done |
Tuesday 6 April | Owl |
|
partly done |
Tuesday 6 April | Day |
|
postponed: vacuum problems |
Tuesday 6 April | Swing |
|
|
Wednesday 7 April | Owl |
|
|
Wednesday 7 April | Day |
|
done. Leak found at O-ring connection between target chamber and collimator box |
Wednesday 7 April | Swing |
|
|
Thursday 8 April | Owl |
| |
Thursday 8 April | Day |
|
|
Thursday 8 April | Swing |
|
|
Friday 9 April | Owl |
|
|
Friday 9 April | Day |
|
|
Friday 9 April | Swing |
|
|
Saturday 10 April | Owl |
|
|
Saturday 10 April | Day |
|
|
Saturday 10 April | Swing |
|
|
Sunday 11 April | Owl |
|
|
Sunday 11 April | Day |
|
|
Sunday 11 April | Swing |
|
|
Monday 12 April | Owl |
|
|
Monday 12 April | Day |
|
|
Monday 12 April | Swing |
|