Difference between revisions of "Shift Checklist"

From PREX Wiki
Jump to navigationJump to search
Line 1: Line 1:
 
<span style="color:red">In the process of editing and updating this page. Please contact Juliette Mammei <B>[mailto:crowder@jlab.org?Subject=PREXwiki crowder@jlab.org]</B> with questions or suggestions.</span>
 
<span style="color:red">In the process of editing and updating this page. Please contact Juliette Mammei <B>[mailto:crowder@jlab.org?Subject=PREXwiki crowder@jlab.org]</B> with questions or suggestions.</span>
 
<br><br>
 
<br><br>
[https://prex.jlab.org/wiki/index.php/Main_Page <B>PREX Main</B>]<< [[Information for Shift Takers]] << [[Shift Taker Responsibilities]]
+
[https://prex.jlab.org/wiki/index.php/Main_Page <B>PREX Main</B>]<< [[Information for Shift Takers]]
  
 
== Finding the checklist ==
 
== Finding the checklist ==

Revision as of 16:16, 8 June 2019

In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.

PREX Main<< Information for Shift Takers

Finding the checklist

  • Open the checklist
  • If you are not already logged in, do so by clicking in the upper right of the page
  • You should now be able to click Log in the upper left
  • In log mode, you will be able to add notes in the boxes at the right
  • Click the checkbox at the left of each item once it is complete

Item Instructions

  • Entering shift info
    • Enter the names of the shift workers (Shift leader, Target operator, Analysis expert)
    • Indicate which shift the checklist is for (day, swing, or owl)
  • Information about the beam
    • Is alarm handler running on hacweb7?
    • Is the volume up on hacweb7? (both hardware and software)
    • Beam Energy (GeV)
    • Beam current (µA)
    • Downstream raster (B) on? Yes/No
    • Raster size (x:y mm, see log 3654466 )?
    • Fast feedback on? Yes/No
    • Beam Position Monitor X/Y (mm) A
    • Beam Position Monitor X/Y (mm) E (BPM B in Hall A Tools)
    • BCM temperature (K) (PV, PS, Thermocouple) If these differ by +/-.5 from (110.0,110.0,115.0) contact RC and halog
    • Arc energy NMR locked? ( (Goto ARC or the "Field Management Screen", and verify if the box locked is ON/OFF))
    • VESDA System OK? (VESDA is the smoke/fire detection and alarm system. Check the Hall A VESDA Console on the wall behind the door
    • Current Target
    • Argon pressure (psi)
    • Ethane pressure (psi)
    • CO2 pressure (psi)
    • Visual Hall Inspection OK?
    • Truck ramp door closed ( use the camera to see the door from mirror)?
    • Septum current (A) and polarity?
    • Upstream/downstream corrector currents (A) ?
  • Left Arm Checks
  • Right Arm Checks

Latest run type (Test, Physics,..) Is the auto replay script running (ask the analysis expert)? Is the APEX run list (in a white binder) completed? Please attach the left/right HV and Scalers Screenshots to the shift report Time of beginning of latest run (RHRS) Latest run number Dead time (%) Beamtime accounting table submitted? Empty drip tray and place mug under spout on coffee maker