Difference between revisions of "RunPlanDaily"
From PREX Wiki
Jump to navigationJump to searchCiprian Gal (talk | contribs) |
Ciprian Gal (talk | contribs) |
||
Line 23: | Line 23: | ||
|- style="background: plum" | |- style="background: plum" | ||
| Swing | | Swing | ||
+ | | Vacuum connections between US pipe and target and between target and collimator box. | ||
| | | | ||
− | |||
|- | |- | ||
| rowspan="3" | Tuesday, June 18 | | rowspan="3" | Tuesday, June 18 | ||
| Owl | | Owl | ||
− | | Pump down the entire region | + | | Pump down the entire pivot to dump region |
| | | | ||
|- | |- |
Revision as of 15:25, 17 June 2019
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, June 17 | Owl | ||
Day | Last day for planned collaboration work in Hall. | Expecting 2A alignment | |
Swing | Vacuum connections between US pipe and target and between target and collimator box. | ||
Tuesday, June 18 | Owl | Pump down the entire pivot to dump region | |
Day | Expecting 2B alignment | ||
Swing | Hall Closed. Final Checklist. | ||
Wednesday, June 19 | Owl | Possible first beam in Hall A | |
Day | |||
Swing | |||
Thursday, June 20 | Owl | ||
Day | |||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting