Line 57: | Line 57: | ||
|- | |- | ||
| Day | | Day | ||
− | | | + | | Tuning |
− | | | + | | |
|- | |- | ||
| Swing | | Swing | ||
− | | Low current commissioning | + | | Tune up and Low current commissioning. |
| | | | ||
|- | |- | ||
| rowspan="3" | Friday, June 21 | | rowspan="3" | Friday, June 21 | ||
| Owl | | Owl | ||
− | | Low current commissioning | + | | Low current commissioning. Started optics |
− | | | + | | Commissioned 45deg and 90deg targets. Calibrated ion chambers. Bullseye scan. |
|- | |- | ||
| Day | | Day |
Revision as of 10:51, 21 June 2019
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Monday, June 17 | Owl | ||
Day | Last day for planned collaboration work in Hall. | Expecting 2A alignment | |
Swing | Vacuum connections between US pipe and target and between target and collimator box. | ||
Tuesday, June 18 | Owl | ||
Day | Pump down the entire pivot to dump region; Expecting 2B alignment | ||
Swing | Target software checks | ||
Wednesday, June 19 | Owl | ||
Day | Hall Closed. Final Checklist. Possible first beam in Hall A | ||
Swing | Continue beam in Hall A for tuning. Start low beam checkout. | ||
Thursday, June 20 | Owl | Continue low beam current checkout. | Completed Collimator search. |
Day | Tuning | ||
Swing | Tune up and Low current commissioning. | ||
Friday, June 21 | Owl | Low current commissioning. Started optics | Commissioned 45deg and 90deg targets. Calibrated ion chambers. Bullseye scan. |
Day | High current + Compton rate tuning. Opportunistic: Beam Modulation (Paul K), Low current cavity (Ye) | High current calibration after tuning | |
Swing | Restart Optics (Seamus, Sanghwa) | Detector checkout. Basic run quality plot macro needed. | |
Saturday, June 22 | Owl | Optics (Bob, Ye? ) | |
Day | Quartz Alignment (Dustin). Rate Studies (KK) | ||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting