| Day | | Day | ||
| 50 microAmp production, PQB study, FFB test | | 50 microAmp production, PQB study, FFB test | ||
− | | | + | | full survey to solve the RHRS Q2, Moller DAQ, BCM? |
|- | |- | ||
|-style="background: #FCF3CF; | |-style="background: #FCF3CF; |
Revision as of 15:08, 18 July 2019
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Tuesday, July 16 | Owl | MOLLER Polarimeter and FFB commissioning | |
Day | production after pass change | ||
Swing | change IHWP ('out'), BPM and BCM calibration (Caryn) | Done | |
Wednesday, July 17 | Owl | Production with 50uA with Aq, BMW and Energy-mode:'RF-off' | |
Day | HallB tuning no beam and frame hunting I | ||
Swing | frame hunting II, current scan, Detector and SAM calibration and 70uA production with 12x7.2 raster | ||
Wednesday, July 18 | Owl | IA, PITA scan, 50uA production with with Aq (HallA and C), BMW and FFB off | |
Day | 50 microAmp production, PQB study, FFB test | full survey to solve the RHRS Q2, Moller DAQ, BCM? | |
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting