! style="width:10%"| Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status | ! style="width:10%"| Day, Date || style="width:10%"| Shift|| style="width:30%"| Tasks (Responsible Party) || style="width:30%"| Status | ||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
− | |||
|- | |- | ||
| rowspan="3" | Sunday, July 21 | | rowspan="3" | Sunday, July 21 |
Revision as of 14:36, 23 July 2019
In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.
PREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Status |
---|---|---|---|
Sunday, July 21 | Owl | production at 50uA | RHRS Q2 magnet is down |
Day | production at 50uA | RHRS Q2 magnet is down | |
Swing | Qsqr measurement and production at 50uA | RHRS Q2 magnet is down | |
Monday, July 22 | Owl | production at 50uA, Moller measurement was paused | LCW leak in the west arc |
Day | control access for Q2 magnet, change quartz at LHRS and put both HRS S0 back with counting mode | LCW leak >10 hours | |
Swing | Qsq measurement, Detector alignment at low current. | 1 hour |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting