* Take counting runs on both arms (LHRS and RHRS) atleast 200k events
 
* Take counting runs on both arms (LHRS and RHRS) atleast 200k events
 
* To analyze the runs:
 
* To analyze the runs:
** ssh -Y a-onl@aonl
+
** ssh -Y a-onl@aonl1
 
** goprex
 
** goprex
 
** analyzer -l
 
** analyzer -l
 
** .x setup2.C(runnumber,200000)
 
** .x setup2.C(runnumber,200000)
 
* When you are done with taking counting data '''turn OFF''' the '''DN-Quartz (MAIN) detectors HVs'''
 
* When you are done with taking counting data '''turn OFF''' the '''DN-Quartz (MAIN) detectors HVs'''
* For safety, set their HV to production level at the end
+
*'''NOTE:''' never turn ON '''DN-Quartz''' HVs during high current production running keeping them at higher HV (they will die)
 +
* For safety, set their HV to production level (~900V) at the end
 +
* To produce plots:
 +
** In a-onl@aonl1 machine:
 +
** cd devi/crex/alignment
 +
** analyzer prex_counting/prexLHRS_runNumber_200000.root for LHRS
 +
** analyzer prex_counting/prexRHRS_runNumber_200000.root for RHRS
 +
** .x alignDS.C
 +
** Look into the elastic peak and read the edge of quartz (the intersection of red and blue histograms in "Projected x on detector plane" plot)
 +
** Zoom in to see the precise edge

Revision as of 14:15, 13 December 2019

  • Set the HV for DN-Quartz (MAIN) detectors in both arms to -1900V (as explained in HVgui)
  • Enable the HV channels
  • Turn ON scintillators
  • Turn ON VDCs (NOTE:Make sure the scintillator rate is below 500k before turning VDC ON)
  • Take counting runs on both arms (LHRS and RHRS) atleast 200k events
  • To analyze the runs:
    • ssh -Y a-onl@aonl1
    • goprex
    • analyzer -l
    • .x setup2.C(runnumber,200000)
  • When you are done with taking counting data turn OFF the DN-Quartz (MAIN) detectors HVs
  • NOTE: never turn ON DN-Quartz HVs during high current production running keeping them at higher HV (they will die)
  • For safety, set their HV to production level (~900V) at the end
  • To produce plots:
    • In a-onl@aonl1 machine:
    • cd devi/crex/alignment
    • analyzer prex_counting/prexLHRS_runNumber_200000.root for LHRS
    • analyzer prex_counting/prexRHRS_runNumber_200000.root for RHRS
    • .x alignDS.C
    • Look into the elastic peak and read the edge of quartz (the intersection of red and blue histograms in "Projected x on detector plane" plot)
    • Zoom in to see the precise edge