Jump to navigationJump to searchLine 9: | Line 9: | ||
** analyzer -l | ** analyzer -l | ||
** .x setup2.C(runNumber,200000) | ** .x setup2.C(runNumber,200000) | ||
− | |||
− | |||
− | |||
* To produce plots: | * To produce plots: | ||
** In a-onl@aonl1 machine: | ** In a-onl@aonl1 machine: | ||
Line 20: | Line 17: | ||
** Look into the elastic peak and read the edge of quartz (the intersection of red and blue histograms in "Projected x on detector plane" plot) | ** Look into the elastic peak and read the edge of quartz (the intersection of red and blue histograms in "Projected x on detector plane" plot) | ||
** Zoom in to see the precise edge | ** Zoom in to see the precise edge | ||
+ | * When you are done with taking counting data '''turn OFF''' the '''DN-Quartz (MAIN) detectors HVs''' | ||
+ | *'''NOTE:''' never turn ON '''DN-Quartz''' HVs during high current production running keeping them at higher HV (they will die) | ||
+ | * For safety, set their HV to production level (~900V) at the end |
Revision as of 14:16, 13 December 2019
- Set the HV for DN-Quartz (MAIN) detectors in both arms to -1900V (as explained in HVgui)
- Enable the HV channels
- Turn ON scintillators
- Turn ON VDCs (NOTE:Make sure the scintillator rate is below 500k before turning VDC ON)
- Take counting runs on both arms (LHRS and RHRS) atleast 200k events
- To analyze the runs:
- ssh -Y a-onl@aonl1
- goprex
- analyzer -l
- .x setup2.C(runNumber,200000)
- To produce plots:
- In a-onl@aonl1 machine:
- cd devi/crex/alignment
- analyzer prex_counting/prexLHRS_runNumber_200000.root for LHRS
- analyzer prex_counting/prexRHRS_runNumber_200000.root for RHRS
- .x alignDS.C
- Look into the elastic peak and read the edge of quartz (the intersection of red and blue histograms in "Projected x on detector plane" plot)
- Zoom in to see the precise edge
- When you are done with taking counting data turn OFF the DN-Quartz (MAIN) detectors HVs
- NOTE: never turn ON DN-Quartz HVs during high current production running keeping them at higher HV (they will die)
- For safety, set their HV to production level (~900V) at the end