RunPlanDaily

From PREX Wiki
Jump to navigationJump to search

In the process of editing and updating this page. Please contact Juliette Mammei crowder@jlab.org with questions or suggestions.

PREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Monday, June 17 Owl
Day Last day for planned collaboration work in Hall. Expecting 2A alignment
Swing Vacuum connections between US pipe and target and between target and collimator box.
Tuesday, June 18 Owl Pump down the entire pivot to dump region
Day Expecting 2B alignment
Swing Hall Closed. Final Checklist.
Wednesday, June 19 Owl Possible first beam in Hall A
Day
Swing
Thursday, June 20 Owl
Day
Swing

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting