February 2 2020

Daily Meeting BlueJeans


Production Run List - Slug 126 - IHWP IN - Flip-RIGHT - Production

continue slug 126 from February 1:


Production Run List - Slug 127 - IHWP OUT - Flip-RIGHT - Production

this slug at about 4 am

Non-Production Runs and Bad Runs

Pedestal/Calibrations Updates

Issues

  • very large asym_bpm2i01WS_mean in slug 127: ~13.8 ppm (compared to previous value of < 5 ppm)
  • due to work in arc 8 box supply, no beam at all during the day and swing shift, beam comes back at about 21:30; but beam spot size tuning and compton work blocks production until 1:45 am the next day

Updates