PREX Run Plan

Part I: List of Tasks

Here is a list of tasks in approximate time order, with person(s) responsible, approximate amount of time required, and comments about the conditions or needs. The time will, in most cases, be broken up into manageable chunks.

  • Basic Beam Setup -- Jay Benesch, Bteam
  • Source and Parity Quality Beam -- Kent Paschke, Mark Dalton, Rupesh Silwal
  • Septum Commissioning -- Bob Michaels, John LeRose
    • Verify septum does not steer beam
    • Thin target, low-current checks
  • Water Cell and Optics of HRS+Septum -- Nilanga Liyanage

Part II: Schedule