RunPlanDaily
From PREX Wiki
Jump to navigationJump to searchDaily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently as the situation on the ground changes.
Last update: Feb 3, 2010. (a work in progress)
Date (2010) | Shift | Activity | Responsible |
---|---|---|---|
03/11 | day | Restore Beam | B-team |
03/11 | swing | Injector Work | K. Paschke |
03/12 | owl | Injector Work | K. Paschke |
03/12 | day | Compton Tuning | A. Camsonne |
03/12 | swing | Septum Checks | R. Michaels |
03/13 | owl | Detector, Optics | N. Liyanage |
03/13 | day | Compton, Moller Commis. | S. Nanda, S. Glamazdin |
03/13 | swing | Compton, Moller Commis. | S. Nanda, S. Glamazdin |
03/14 | owl | Optics | N. Liyanage |
03/14 | day | Optics | N. Liyanage |