Daily Run Plan

Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently as the situation on the ground changes.

Last update: Feb 3, 2010.   (a work in progress)

Daily Run Plan for PREX
Date (2010) Shift Activity Responsible
03/11 day Restore Beam B-team
03/11 swing Injector Work K. Paschke
03/12 owl Injector Work K. Paschke
03/12 day Compton Tuning A. Camsonne
03/12 swing Septum Checks R. Michaels
03/13 owl Detector, Optics N. Liyanage
03/13 day Compton, Moller Commis. S. Nanda, S. Glamazdin
03/13 swing Compton, Moller Commis. S. Nanda, S. Glamazdin
03/14 owl Optics N. Liyanage
03/14 day Optics N. Liyanage