Task List, Preparing for 2019 Run
Radiation Benchmarking
- ERR recommendation
- Contact Dave Hamlette, Javier Gomez to discuss metrics for benchmark
Design and Simulation
Base design, v3 Benchmarks.
<<Complete by March 16>>
- Need new benchmarks (accounting for updated geometry (dump, HRS) and SAMS
- for PREX-I, HAPPEX-II, PREX-2, CREX (and others?)
- on HRS detectors, under HRS detectors, Hall Lid or Hall Wall total ("whole hall"), and Hall Lid skyshine estimates
- prex2-v3:
- prex-2 dump, with shield
- no SAMS, or alternative SAMs?
- crex2-v3:
- (same with 48Ca target and 2.1 GeV)
- prex1-"??name??"
- PREX-I collimator
- PREX-I chamber? (not as important)
- PREX-I dump (with KW correction)
- no HDPE, no SkyshineShield
- Full size HRS det and structure, match prex2
- FULL PREX-I SAMS
- HAPPEX-II - ??name??
- HAPPEX-II collimator (same as PREX-I?)
- PREX-I dump (with KW correction)
- 3.2 GeV, 20cm LH2
- PREX-I chamber (not as important)
- no HDPE, no SkyshineShield
- Full size HRS det and strucutre, match prex2 sim
- FULL PREX-I SAMS
- PV-DIS?
- HAPPEX-3?
- TRITIUM (11 GeV)?
- DVCS?
Geometry, Next iteration.
<<Complete by April 6>>.
- realistic gaps around dump shield
- target chamber
- collimator chamber to match design
- HDPE around target to match design
- modified SAM design?
Magnetic Shielding
- Evaluate B-field in Q1 beampipe with only one Q1 energized
- Evaluate the Tritium-Magnetic-shield design
- Evaluate mag shield additions for upstream/downstream septum beampipe
O-Ring damage
- Plots:
- E-weighted, electron only plots from beamline det an o-ring det
- tables to arrive at integrated grays
- hall-lid det x0/y0 plot to show enhancement from full SAMS
- get info on O-ring from engineering. (material, lifetime expectations, also when did this appear?)
- Full base design (Feb18), but w/o dump shield
- Use Al around O-ring
- No SAMS
- PREX-I SAMS
- test 1/2 size O-ring (PREX) (PREX-I SAMS)
- Done, but dumb results. Compare 1/2 size O-ring with 1/2 of full size O-ring.
- test no material around O-ring (PREX) (PREX-I SAMS)
- CREX
- No SAMS
- PREX-I SAMS
- check beam-offset run
- Use Al around O-ring
- Results for alternative SAM configs
- Final estimate use full base design (Feb18), including dump shield
- PREX-2
- CREX
SAM redesign
- calculate rates vs angle
- calculate doses vs angles
- get details on beer can, make default design including welding
- Attempt final design
- Propose/Exam alternative SBMs
Activation Estimation
- Downstream septum beampipe flange, contact dose
- Downstream septum beampipe flange, whole body dose
- CREX activation estimates
- HDPE activation.
- DUST ACTIVATION?
HDPE parameters
- Total / peak radiation dose. Damage?
- spec non-flamable HDPE, or devise fireproofing
Thermal Neutrons:
- count thermal/near thermal (<1eV rate), assume 8MeV / n energy release, compare to E&M power
- plot sources of thermal neutrons in hall, using hall-lid and HRS-platform detectors
- consider effect of 5% boron
- calculate thermal neutrons at Compton polarimeter
Spectrometer Optics Design
- FOM optimization
- Q1 collimator cut-out
Analysis Chain
- First attempt at new analyzer <<June deadline>>
DAQ / Slow Controls
- Multicrate running.
- Sync monitor.
- Test fast event transfer to online monitor/feedback at 240 Hz
- ADC maintenance - number of channels, etc
- BCM, digital cavity receivers - verify functioning
- slow controls
Beam Modulation System
- Testing of installed hardware
- Evaluation of accelerator interface software
- Coordination with other halls, scheduling committee
- Beam modulation software (Hall)
- modulation process
- slow control / monitoring
- DAQ interface
Detector Stack
GEMs
Integrating Detectors
- Complete Design
- Linearity Studies
- Plan for Blind tubes in spectrometer hut?
Detector Mounting Hardware
Polarized Source / Injector
- RTP / KD*P?
- Test setting limits on spot size
- Outline configuration procedure and run-planning
- spin-flipper studies
Moller Polarimeter
- 1 GeV Optics
- simulation for acceptance evaluation
- target system installation
- Plan to establish high-precision Moller polarimetry (ERR recommendation)
Compton Polarimeter
- Plan to establish high-precision Compton polarimetry (ERR recommendation)
- Laser Maintenance and improvement, summer 2018
- e- detector, final plan
Documentation
Run planning
- Plan for beam alignment (collimator, dump) and raster commissioning (ERR recommendation)
- Comprehensive List / Planning for survey and alignment tasks
- Watercell (pointing) runplan
- optics runplan
- detector alignment run plan
Formal
- Finalize OSPs (ERR recommendation)