RunPlanDaily CREX
From PREX Wiki
Revision as of 17:56, 13 December 2019 by Juliette Mammei (talk | contribs) (→Current Daily Run Plans)
CREX Main << Run Coordinator Tools
Current Daily Run Plans
The current day is indicated by a color.
Day, Date | Shift | Tasks (Responsible Party) | Comments/Status |
---|---|---|---|
Friday, December 13 | Owl | high-current commissioning | |
Day | Spin dance cancelled; production when have beam | ||
Swing | high-current commissioning/pre-production | Goal is to get the beamline instrumentation ready for PQB to get a look at regression and widths, etc. (pre-production) | |
Saturday, December 14 | Owl | Production | |
Day | Production | may plan to do optics with water cell at some point | |
Swing | Production | ||
Sunday, December 15 | Owl | Production | |
Day | Production | ||
Swing | Production | ||
Monday, December 16 | Owl | Production | |
Day | Production | ||
Swing | Production | ||
Tuesday, December 17 | Owl | Production | |
Day | No beam if we have good running over weekend and Hall C is ready | ||
Swing | |||
Wednesday, December 18 | Owl | ||
Day | |||
Swing |
Instructions for RC
- Let the day shift know what to do while you attend the MCC meeting
- Copy the daily run plans for the previous week to the Run plan history CREX
- Copy the Run Plan Template table to this page and change the dates
- Update the plan above (if necessary) after the MCC meeting