RunPlanDaily
From PREX Wiki
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently as the situation on the ground changes.
Last update: Feb 3, 2010. (a work in progress)
Date (2010) | Shift | Activity | Responsible |
---|---|---|---|
03/11 | day | Restore Beam | B-team |
03/11 | swing | Injector Work | K. Paschke |
03/12 | owl | Injector Work | K. Paschke |
03/12 | day | Compton Tuning | A. Camsonne |
03/12 | swing | Septum Checks | R. Michaels |
03/13 | owl | Detector, Optics | N. Liyanage |
03/13 | day | Compton, Moller Commis. | S. Nanda, S. Glamazdin |
03/13 | swing | Compton, Moller Commis. | S. Nanda, S. Glamazdin |
03/14 | owl | Optics | N. Liyanage |
03/14 | day | Optics | N. Liyanage |