RunPlanDaily
From PREX Wiki
Revision as of 21:38, 20 March 2010 by Rich Holmes (talk | contribs) (→Daily Run Plan: 3/21 owl, day)
Daily Run Plan
Here are details of the daily run plan. See also the global Run Plan. The person responsible should ensure that a crew of experts is available for the shift. This schedule will be updated frequently by the Run Coordinator as the situation on the ground changes.
Date (2010) | Shift | ---------- Activity (Responsible) ---------- | --- Status --- |
---|---|---|---|
03/19 | day | pump down; Møller, Compton, septum install; Q2 repair Insert sieve. (Techs) |
|
03/19 | swing | Beam restore (B-team) | done |
03/20 | owl |
also:
All at 1-2 µA.
"Usual" polarity |
done |
03/20 | day | Beam off & hall open 9:00 am Quads repair; Compton install; GEM install; signals debugging. Leave sieves in. (Techs) |
done |
03/20 | swing |
|
in progress |
3/21 | owl |
At <~ 100 nA up to few µA. |
not done |
3/21 | day |
Page Jack Segal if long access. |
not done |