20190624-Analyzer-Mtg
From PREX Wiki
Back to Main Page >> Analyzer_Meeting
previous meeting << >> following meeting
Logistic information
Meeting room at JLab: CH Conference room (on the accelerator side).
BlueJeans calling instructions: Toll-Free Number (U.S.& Canada): 888-240-2560 International toll number: 408-740-7256 Bluejeans CODE: 385 600 867 Bluejeans link: https://bluejeans.com/385600867
Agenda
Analyzer code updates
- Recent branch activity & pull requests
- Burst analysis development: several pulls should be ready to merge, but my comparison to previous versions is not yet working because the print-runningsum doesn't work due to the runningsum changes. Rakitha will look at it.
- Burp cut: Robert has pushed a set of changes that seems to work, and a quick comparison with previous results shows agreement. May need a little further refinement.
- Activating the blinder
- Online analyzer doesn't get the EPICS data properly. May b=either use EPICS calls directly, or an independent run-dependent blinder for the online displays
- miniruns & regression analysis
- The burst developments
- feedback
- Amali had been starting to look at adding the new variables; Rakitha can help
- Beam modulation
- Updates to the bmwClient
- Client is basically working now, may need some tuning
- Decoding and BMOD tree extraction
- New decoder is in operations. May need to recheck channel map
- Post-production extractor is in progress
- Still intend to do the extraction from JAPAN as part of first pass.
- Updates to the bmwClient
Hardware/DAQ tasklist
- EPICS run-start and fast logger (and EPICS decoder to slow tree)
- automatic production of run-dependent database
- Up and running, Home page: https://hallaweb.jlab.org/rcdb
- WAC comment gui, and WAC DB edit tool
- Just a couple more example scripts to add
- e-logbook entries
- All three are now active
- Green Monster rework: Robert
- An "official" copy is installed under ~apar/devices/PyGreenMonster. Later we should import it into the DAQ repo.
- Timing: mostly understood, still small mysteries (LNE)
- I think some CRLs still have module initialization at Prestart, so we need to pull that out.
- Synchronization-check system. w/help from Ed Jastrzembski
- Scaler-based sync for injector is better, but still not 100%; see [1] and attachment
- New digital system will be available some time after the run starts
- Pedestal studies, aka cross-talk
- alarms like end-of-run voice
- Data quality alarm concept: a realtime engine will report problems via text output on a periodic basis (~few seconds), the alarm display will poll this and warn the shift crew.
- "End-of-run" voice would be tied to coda transitions
- Clean up cabling, labels, fasteners - First need to examine all signals
- CC: working on it.
- Document everything. Circuit diagrams, cable map, "how to".
- CC: will make circuit diagrams.
- Remote power supply cycling capability:
- CC: trying to figure out how to use them (talked with Jack).
ReSpin of APEX runs
- Aggregator Sakib:
- Pass 2: Tao
Present
Phone: