Logistic information

Meeting room at JLab: CH Conference room (on the accelerator side).

 BlueJeans calling instructions:
 Toll-Free Number (U.S.&  Canada):  888-240-2560
 International toll number:         408-740-7256
 Bluejeans CODE:                  385 600 867
 Bluejeans link: https://bluejeans.com/385600867

Agenda

Analyzer code updates

  1. Recent branch activity & pull requests
    • Burst analysis development: several pulls should be ready to merge, but my comparison to previous versions is not yet working because the print-runningsum doesn't work due to the runningsum changes. Rakitha will look at it.
    • Burp cut: Robert has pushed a set of changes that seems to work, and a quick comparison with previous results shows agreement. May need a little further refinement.
  2. Activating the blinder
    • Online analyzer doesn't get the EPICS data properly. May b=either use EPICS calls directly, or an independent run-dependent blinder for the online displays
  3. miniruns & regression analysis
    • The burst developments
  4. feedback
    • Amali had been starting to look at adding the new variables; Rakitha can help
  5. Beam modulation
    • Updates to the bmwClient
      • Client is basically working now, may need some tuning
    • Decoding and BMOD tree extraction
      • New decoder is in operations. May need to recheck channel map
      • Post-production extractor is in progress
      • Still intend to do the extraction from JAPAN as part of first pass.

Hardware/DAQ tasklist

  1. EPICS run-start and fast logger (and EPICS decoder to slow tree)
  2. automatic production of run-dependent database
  3. e-logbook entries
    • All three are now active
  4. Green Monster rework: Robert
    • An "official" copy is installed under ~apar/devices/PyGreenMonster. Later we should import it into the DAQ repo.
  5. Timing: mostly understood, still small mysteries (LNE)
    • I think some CRLs still have module initialization at Prestart, so we need to pull that out.
  6. Synchronization-check system. w/help from Ed Jastrzembski
    • Scaler-based sync for injector is better, but still not 100%; see [1] and attachment
    • New digital system will be available some time after the run starts
  7. Pedestal studies, aka cross-talk
  8. alarms like end-of-run voice
    • Data quality alarm concept: a realtime engine will report problems via text output on a periodic basis (~few seconds), the alarm display will poll this and warn the shift crew.
    • "End-of-run" voice would be tied to coda transitions
  9. Clean up cabling, labels, fasteners - First need to examine all signals
    • CC: working on it.
  10. Document everything. Circuit diagrams, cable map, "how to".
    • CC: will make circuit diagrams.
  11. Remote power supply cycling capability:
    • Most things we need on them are now on them. The spectromater parity crates are not, due to power rating of the remote strips.

Prompt analysis toolchain

Present

Phone:

Excused