Copy weekly run plan tables here. Most recent at the top.


Day, Date Shift Tasks (Responsible Party) Status
Friday, June 14 Owl
Day
Swing
Monday, June 17 Owl
Day Last day for planned collaboration work in Hall. Expecting 2A alignment
Swing Vacuum connections between US pipe and target and between target and collimator box.
Tuesday, June 18 Owl
Day Pump down the entire pivot to dump region; Expecting 2B alignment
Swing Target software checks
Wednesday, June 19 Owl
Day Hall Closed. Final Checklist. Possible first beam in Hall A
Swing Continue beam in Hall A for tuning. Start low beam checkout.
Thursday, June 20 Owl Continue low beam current checkout. Completed Collimator search.
Day Tuning
Swing Tune up and Low current commissioning.
Friday, June 21 Owl Low current commissioning. Started optics Commissioned 45deg and 90deg targets. Calibrated ion chambers. Bullseye scan.
Day High current + Compton rate tuning.
Swing High current calibration after tuning (Caryn). Low current commissioning. Restart Optics (Seamus, Sanghwa, Ryan) Basic run quality plot macro needed (Sanghwa).
Saturday, June 22 Owl Opportunistic: Beam Modulation (Paul K, Vectoria) ESR 15K helium issue, scattering chamber vacuum degration investigation
Day Optics.
Swing Low current cavity (Ye, Cip). Minimum chase.
Sunday, June 23 Owl Inner edge search (Bob, Chandan, Kent). Q2 measurement with Pb target (Bob?). Opportunistic: Beam Modulation (Paul K, Vectoria) Inner edge search DONE.
Day Minimize width.
Swing Minimize width. Minimum chase.
Monday, June 24 Owl Quartz align; quartz rate. (Dustin)
Day Optics verification. ESR 15K helium repair is ongoing.
Swing No beam.