RunPlanDaily CREX

From PREX Wiki
Jump to navigationJump to search



CREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Status
Monday, November 25 Owl No shift
Day No shift
Swing No shift
Tuesday, November 26 Owl No shift
Day Compton work
Swing Compton work
Wedsday, November 27 Owl No shift
Day No shift
Swing No shift
Thursday, November 28 Owl No shift
Day Eat Turkey
Swing Eat more...
Friday, November 29 Owl No shift
Day No shift
Swing
Saturday, November 30 Owl No shift
Day No shift
Swing No shift
Sunday, December 1 Owl No shift
Day Moller Measurement
Swing Moller Measurement
Monday, December 2 Owl No shift
Day Magnet work
Swing Magnet work
Tuesday, December 3 Owl No shift
Day Magnet work
Swing Magnet work
Wednesday, December 4 Owl No shift
Day Magnet work...
Swing Magnet work...
Thursday, December 5 Owl No shift
Day RF stress test to C/ crappy 1uA to A (if magnets fixed)
Swing low current commissioning
Friday, December 6 Owl low current commissioning
Day spin dance
Swing spin dance
Saturday, December 7 Owl low current commissioning/ Q2 measurement and Spectrometer rescattering https://prex.jlab.org/wiki/index.php/RescatteringPlan
Day commissioning
Swing commissioning
Sunday, December 8 Owl commissioning
Day commissioning
Swing commissioning
Monday, December 9 Owl commissioning
Day commissioning
Swing commissioning
Tuesday, December 10 Owl ...HallC 1 pass? at some point
Day ...HallC 1 pass? at some point
Swing ...HallC 1 pass? at some point

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting