RunPlanDaily CREX

From PREX Wiki
Jump to navigationJump to search



CREX Main << Run Coordinator Tools

Global Run Plan

Current Daily Run Plans

The current day is indicated by a color.

Day, Date Shift Tasks (Responsible Party) Comments/Status
Friday, December 13 Owl high-current commissioning
Day spin dance (if not already done)? OR more high-current commissioning; also possible loss of beam for ramp test in Hall C (2-3 hours)
Swing high-current commissioning/pre-production Goal is to get the beamline instrumentation ready for PQB to get a look at regression and widths, etc. (pre-production)
Saturday, December 14 Owl
Day Will lose beam at some point so Hall C can go to 5 pass Note these "no beam" shifts are subject to a change in start time
Swing No beam?
Sunday, December 15 Owl No beam?
Day No beam?
Swing No beam?
Monday, December 16 Owl No beam?
Day No beam?
Swing No beam?
Tuesday, December 17 Owl No beam?
Day Get beam back in Hall A?
Swing
Wednesday, December 18 Owl
Day
Swing

Previous Daily Run Plans

Instructions for RC

  • Let the day shift know what to do while you attend the MCC meeting
  • Copy the daily run plans for the previous week to the Run plan history CREX
  • Copy the Run Plan Template table to this page and change the dates
  • Update the plan above (if necessary) after the MCC meeting