20190116-Analyzer-Mtg
From PREX Wiki
Jump to navigationJump to searchThe printable version is no longer supported and may have rendering errors. Please update your browser bookmarks and please use the default browser print function instead.
Back to Main Page >> Analyzer_Meeting
previous meeting << >> following meeting
Logistic information
Use blue jeans ID, 415 824 2483, for today
BlueJeans calling instructions: Toll-Free Number (U.S.& Canada): 888-240-2560 International toll number: 408-740-7256 Bluejeans CODE: 419 045 306 Bluejeans link: https://bluejeans.com/419045306
github repository: JAPAN
Agenda
- online plots pullRequest
- regression analysis
- DAQ issues
- 2 ET update from last week
- On the DAQ to-do list
- Point 3 (filenames, etc) was done on Tuesday
- Point 4 (scalers) was done last week
- Point 2 (synch) is in progress, maybe half done
- I'd like to see progress on points 9 (test JAPAN+DAQ) and 8 (Pedestal studies) next.
- Point 11 is somewhat urgent if we want to have time to repair bad modules
- It looks like Adam has taken over point 10 (Greenmonster).
- VQWK adcs
- Other issues
Bob's DAQ tasklist
TO-DO list for Parity DAQ updated Jan 4, 2019
Cameron & Bob: 1, 2, 4, 5, 6, 11, 12, 13 Tao & Cameron: 8, 9 Bob: 3, 6, 10 Cip, Cameron, Tao: 13 1 Timing: mostly understood, still small mysteries (LNE) 2 Synchronization-check system. w/help from Ed Jastrzembski 3 File naming, reset run num, finalize configs (INJ, CH, ALL) 4 Fix scalers on spectrometer crates. 5 clean up cabling, labels, fasteners. 6 Clean up CRL -- eliminate so-called "dirty trick" 7 Check the 7200 scaler setup at injector, find a spare 7200. 8 Pedestal studies, aka cross-talk. 9 Test JAPAN. Need cable map & labels. Possibly maintain "pan" ? 10 Green Monster maintenance. 11 Test spares. Repair bad modules. 12 Document everything. Circuit diagrams, cable map, "how to". 13 Online software, a bit undefined since software is changing. (a) automatic production of run-dependent database (b) alarms like end-of-run voice (Bob) (c) feedback (d) coil-pulsing aka modulation aka dithering (Victoria) (e) panguin (GUI showing real-time plots) (f) prompt analysis (g) e-logbook entries (h) archiving EPICs data Accomplished * Revive all crates. * Deploy all ADCs needed and test each channel. * Build various DAQ configs with subsets of the DAQ crates. * Timing diagram, check timing of external signals and readout. * ET system upgrade, test rate limits, ensure deadtime zero. * Implement Bank structure.