Difference between revisions of "20190213-Analyzer-Mtg"
From PREX Wiki
(→Bob's DAQ tasklist) |
Ciprian Gal (Talk | contribs) (→Agenda) |
||
(One intermediate revision by the same user not shown) | |||
Line 14: | Line 14: | ||
== Agenda == | == Agenda == | ||
# New branch "operations" | # New branch "operations" | ||
− | #* | + | #* PK: Should be checked out as the production analyzer on adaq |
− | #* | + | #* PK: Only parameter file changes should go to this branch; all other development should be based on "develop" |
− | #* | + | #* PK: once APEX goes into production and we have gone through all the calibrations we should push config changes back to develop |
# online plots | # online plots | ||
− | #* | + | #* CC: wiki page for running japan [[JAPAN_Doc_Portal#Using_JAPAN_on_adaq_cluster]] |
+ | #* WD: the map file seems to have been restored. Still woking to make sure it is ready for prime time. | ||
+ | #* PK: we still are working on getting Japan to work with the double ET system. | ||
+ | #* CG: we should keep the macro folder in panguin for configuration files only. | ||
# regression analysis | # regression analysis | ||
− | #* | + | #* PK: RR has all the 3 data handler classes working. Is now setting up configurations to run on prex data. |
# feedback | # feedback | ||
− | #* | + | #* PK: talked to Amali and showed her what Japan feedback is doing and pointed her to where she should be looking (including the epics communications class) |
+ | #* PK: we will turn off the compilation of the feedback in the develop branch and have it working only in the operations branch. | ||
# DAQ issues | # DAQ issues | ||
− | #* | + | #* Cleaning counting house crate |
+ | #** PK: Cameron and I will take a look at it the week of the 24th Feb | ||
# VQWK adcs | # VQWK adcs | ||
− | #* | + | #* PK: Cameron replaced the VQK that had BPM 8 plugged in. And will meet with Chris Cuevas to talk about repair and testing. |
# Pull requests: | # Pull requests: | ||
− | #* | + | #* CG: please do NOT just merge a pull request by yourself. Wait for review. |
# DAQ tasklist: | # DAQ tasklist: | ||
− | #* | + | #* CC: updated below |
− | + | ||
# Other issues | # Other issues | ||
− | #* | + | #* Change to the PC HVs |
− | #** | + | #** KP: create new feedback script and remove the +x from all the other scripts |
== Bob's DAQ tasklist == | == Bob's DAQ tasklist == | ||
Line 74: | Line 78: | ||
== Present == | == Present == | ||
− | + | Cameron C, Robert R, Tao Y, Iris H, Ciprian G, Paul K, Ye T, Devi A, Kent P, Wouter D, Jinlong Z, | |
===Excused=== | ===Excused=== | ||
[[Category:Meetings]] | [[Category:Meetings]] | ||
[[Category:Analyzer_Meeting]] | [[Category:Analyzer_Meeting]] |
Latest revision as of 15:31, 13 February 2019
Back to Main Page >> Analyzer_Meeting
previous meeting << >> following meeting
Logistic information
Meeting room at JLab: CC L210A (entrance is in the lobby across from the 2nd floor auditorium entrance)
BlueJeans calling instructions: Toll-Free Number (U.S.& Canada): 888-240-2560 International toll number: 408-740-7256 Bluejeans CODE: 419 045 306 Bluejeans link: https://bluejeans.com/419045306
Agenda
- New branch "operations"
- PK: Should be checked out as the production analyzer on adaq
- PK: Only parameter file changes should go to this branch; all other development should be based on "develop"
- PK: once APEX goes into production and we have gone through all the calibrations we should push config changes back to develop
- online plots
- CC: wiki page for running japan JAPAN_Doc_Portal#Using_JAPAN_on_adaq_cluster
- WD: the map file seems to have been restored. Still woking to make sure it is ready for prime time.
- PK: we still are working on getting Japan to work with the double ET system.
- CG: we should keep the macro folder in panguin for configuration files only.
- regression analysis
- PK: RR has all the 3 data handler classes working. Is now setting up configurations to run on prex data.
- feedback
- PK: talked to Amali and showed her what Japan feedback is doing and pointed her to where she should be looking (including the epics communications class)
- PK: we will turn off the compilation of the feedback in the develop branch and have it working only in the operations branch.
- DAQ issues
- Cleaning counting house crate
- PK: Cameron and I will take a look at it the week of the 24th Feb
- Cleaning counting house crate
- VQWK adcs
- PK: Cameron replaced the VQK that had BPM 8 plugged in. And will meet with Chris Cuevas to talk about repair and testing.
- Pull requests:
- CG: please do NOT just merge a pull request by yourself. Wait for review.
- DAQ tasklist:
- CC: updated below
- Other issues
- Change to the PC HVs
- KP: create new feedback script and remove the +x from all the other scripts
- Change to the PC HVs
Bob's DAQ tasklist
TO-DO list for Parity DAQ updated Jan 4, 2019
Cameron & Bob: 1, 2, 4, 5, 6, 11, 12, 13 Tao & Cameron: 8, 9 Bob: 3, 6, 10 Cip, Cameron, Tao: 13 1 Doing - Timing: mostly understood, still small mysteries (LNE) 2 Doing - Synchronization-check system. w/help from Ed Jastrzembski 3 Done - File naming, reset run num, finalize configs (INJ, CH, ALL) 4 Done - Fix scalers on spectrometer crates. 5 To Do - Clean up cabling, labels, fasteners - First need to examine all signals 6 Clean up CRL -- eliminate so-called "dirty trick" 7 Check the 7200 scaler setup at injector, find a spare 7200. 8 Doing - Pedestal studies, aka cross-talk. 9 Done - Test JAPAN. Need cable map & labels. Possibly maintain "pan" ? 10 Green Monster maintenance. 11 Doing - Test spares. Repair bad modules. 12 Doing - Document everything. Circuit diagrams, cable map, "how to". 13 Online software, a bit undefined since software is changing. (a) automatic production of run-dependent database (b) alarms like end-of-run voice (Bob) (c) feedback (d) coil-pulsing aka modulation aka dithering (Victoria) (e) panguin (GUI showing real-time plots) (f) prompt analysis (g) e-logbook entries (h) archiving EPICs data Accomplished * Revive all crates. * Deploy all ADCs needed and test each channel. * Build various DAQ configs with subsets of the DAQ crates. * Timing diagram, check timing of external signals and readout. * ET system upgrade, test rate limits, ensure deadtime zero. * Implement Bank structure.
Present
Cameron C, Robert R, Tao Y, Iris H, Ciprian G, Paul K, Ye T, Devi A, Kent P, Wouter D, Jinlong Z,